Substation / 150 kV

BEERS

Elia Transmission Belgium / Belgium

Latest published values

80 served · 0 withheld

Each row is what the operator’s latest published dataset reports for one combination of direction, technology, measure, firmness and horizon. Hosting-capacity figures are indicative and reflect what operators publish. They are not a connection offer; only the operator can confirm capacity for a specific request.

Latest published capacity values, one row per series
DirectionTechnologyMeasureValueFirmnessHorizonSource date
InjectionGeneration (any)Available3.9 MWFirm, ≤ 0 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionGeneration (any)Available1.3 MWFirm, ≤ 0 % curtailment a year2027 (2027)variant: 70kv26 Sep 2026
InjectionGeneration (any)Available7.4 MWFlexible, ≤ 5 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionGeneration (any)Available6.5 MWFlexible, ≤ 5 % curtailment a year2027 (2027)variant: 70kv26 Sep 2026
InjectionGeneration (any)Available10 MWFlexible, ≤ 10 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionGeneration (any)Available9.7 MWFlexible, ≤ 10 % curtailment a year2027 (2027)variant: 70kv26 Sep 2026
InjectionGeneration (any)Available21.3 MWFlexible, ≤ 20 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionGeneration (any)Available19.2 MWFlexible, ≤ 20 % curtailment a year2027 (2027)variant: 70kv26 Sep 2026
InjectionGeneration (any)Available3.9 MWFirm, ≤ 0 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionGeneration (any)Available1.3 MWFirm, ≤ 0 % curtailment a year2031 (2031)variant: 70kv26 Sep 2026
InjectionGeneration (any)Available8.6 MWFlexible, ≤ 5 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionGeneration (any)Available6.8 MWFlexible, ≤ 5 % curtailment a year2031 (2031)variant: 70kv26 Sep 2026
InjectionGeneration (any)Available11.5 MWFlexible, ≤ 10 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionGeneration (any)Available11.2 MWFlexible, ≤ 10 % curtailment a year2031 (2031)variant: 70kv26 Sep 2026
InjectionGeneration (any)Available28.6 MWFlexible, ≤ 20 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionGeneration (any)Available27.1 MWFlexible, ≤ 20 % curtailment a year2031 (2031)variant: 70kv26 Sep 2026
InjectionSolar PVAvailable6.8 MWFirm, ≤ 0 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionSolar PVAvailable2 MWFirm, ≤ 0 % curtailment a year2027 (2027)variant: 70kv26 Sep 2026
InjectionSolar PVAvailable12.5 MWFlexible, ≤ 5 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionSolar PVAvailable9.2 MWFlexible, ≤ 5 % curtailment a year2027 (2027)variant: 70kv26 Sep 2026
InjectionSolar PVAvailable15.9 MWFlexible, ≤ 10 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionSolar PVAvailable12.2 MWFlexible, ≤ 10 % curtailment a year2027 (2027)variant: 70kv26 Sep 2026
InjectionSolar PVAvailable24.5 MWFlexible, ≤ 20 % curtailment a year2027 (2027)variant: 70kv26 Sep 2026
InjectionSolar PVAvailable24.5 MWFlexible, ≤ 20 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionSolar PVAvailable6.8 MWFirm, ≤ 0 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionSolar PVAvailable5 MWFirm, ≤ 0 % curtailment a year2031 (2031)variant: 70kv26 Sep 2026
InjectionSolar PVAvailable12.9 MWFlexible, ≤ 5 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionSolar PVAvailable9.3 MWFlexible, ≤ 5 % curtailment a year2031 (2031)variant: 70kv26 Sep 2026
InjectionSolar PVAvailable16.3 MWFlexible, ≤ 10 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionSolar PVAvailable12.5 MWFlexible, ≤ 10 % curtailment a year2031 (2031)variant: 70kv26 Sep 2026
InjectionSolar PVAvailable27.3 MWFlexible, ≤ 20 % curtailment a year2031 (2031)variant: 70kv26 Sep 2026
InjectionSolar PVAvailable25.4 MWFlexible, ≤ 20 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionOnshore windAvailable5.2 MWFirm, ≤ 0 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionOnshore windAvailable2.3 MWFirm, ≤ 0 % curtailment a year2027 (2027)variant: 70kv26 Sep 2026
InjectionOnshore windAvailable12 MWFlexible, ≤ 5 % curtailment a year2027 (2027)variant: 70kv26 Sep 2026
InjectionOnshore windAvailable11.3 MWFlexible, ≤ 5 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionOnshore windAvailable18.7 MWFlexible, ≤ 10 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionOnshore windAvailable18.2 MWFlexible, ≤ 10 % curtailment a year2027 (2027)variant: 70kv26 Sep 2026
InjectionOnshore windAvailable47.4 MWFlexible, ≤ 20 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionOnshore windAvailable40.9 MWFlexible, ≤ 20 % curtailment a year2027 (2027)variant: 70kv26 Sep 2026
InjectionOnshore windAvailable5.3 MWFirm, ≤ 0 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionOnshore windAvailable2.3 MWFirm, ≤ 0 % curtailment a year2031 (2031)variant: 70kv26 Sep 2026
InjectionOnshore windAvailable14.6 MWFlexible, ≤ 5 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionOnshore windAvailable14.5 MWFlexible, ≤ 5 % curtailment a year2031 (2031)variant: 70kv26 Sep 2026
InjectionOnshore windAvailable25.3 MWFlexible, ≤ 10 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionOnshore windAvailable22 MWFlexible, ≤ 10 % curtailment a year2031 (2031)variant: 70kv26 Sep 2026
InjectionOnshore windAvailable68.5 MWFlexible, ≤ 20 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionOnshore windAvailable60 MWFlexible, ≤ 20 % curtailment a year2031 (2031)variant: 70kv26 Sep 2026
OfftakeLoad (any)Available4.1 MWFirm, ≤ 0 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
OfftakeLoad (any)Available1.3 MWFirm, ≤ 0 % curtailment a year2027 (2027)variant: 70kv26 Sep 2026
OfftakeLoad (any)Available13.7 MWFlexible, ≤ 5 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
OfftakeLoad (any)Available3.7 MWFlexible, ≤ 5 % curtailment a year2027 (2027)variant: 70kv26 Sep 2026
OfftakeLoad (any)Available27.4 MWFlexible, ≤ 10 % curtailment a year2027 (2027)variant: 70kv26 Sep 2026
OfftakeLoad (any)Available24.8 MWFlexible, ≤ 10 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
OfftakeLoad (any)Available140 MWFlexible, ≤ 20 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
OfftakeLoad (any)Available60 MWFlexible, ≤ 20 % curtailment a year2027 (2027)variant: 70kv26 Sep 2026
OfftakeLoad (any)Available4.1 MWFirm, ≤ 0 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
OfftakeLoad (any)Available1.3 MWFirm, ≤ 0 % curtailment a year2031 (2031)variant: 70kv26 Sep 2026
OfftakeLoad (any)Available90.4 MWFlexible, ≤ 5 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
OfftakeLoad (any)Available3.7 MWFlexible, ≤ 5 % curtailment a year2031 (2031)variant: 70kv26 Sep 2026
OfftakeLoad (any)Available175 MWFlexible, ≤ 10 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
OfftakeLoad (any)Available27.4 MWFlexible, ≤ 10 % curtailment a year2031 (2031)variant: 70kv26 Sep 2026
OfftakeLoad (any)Available175 MWFlexible, ≤ 20 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
OfftakeLoad (any)Available60 MWFlexible, ≤ 20 % curtailment a year2031 (2031)variant: 70kv26 Sep 2026
BidirectionalBatteryAvailable3.9 MWFirm, ≤ 0 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
BidirectionalBatteryAvailable1.3 MWFirm, ≤ 0 % curtailment a year2027 (2027)variant: 70kv26 Sep 2026
BidirectionalBatteryAvailable7.4 MWFlexible, ≤ 5 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
BidirectionalBatteryAvailable3.5 MWFlexible, ≤ 5 % curtailment a year2027 (2027)variant: 70kv26 Sep 2026
BidirectionalBatteryAvailable10 MWFlexible, ≤ 10 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
BidirectionalBatteryAvailable9.7 MWFlexible, ≤ 10 % curtailment a year2027 (2027)variant: 70kv26 Sep 2026
BidirectionalBatteryAvailable21.3 MWFlexible, ≤ 20 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
BidirectionalBatteryAvailable19.2 MWFlexible, ≤ 20 % curtailment a year2027 (2027)variant: 70kv26 Sep 2026
BidirectionalBatteryAvailable3.9 MWFirm, ≤ 0 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
BidirectionalBatteryAvailable1.3 MWFirm, ≤ 0 % curtailment a year2031 (2031)variant: 70kv26 Sep 2026
BidirectionalBatteryAvailable8.6 MWFlexible, ≤ 5 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
BidirectionalBatteryAvailable3.5 MWFlexible, ≤ 5 % curtailment a year2031 (2031)variant: 70kv26 Sep 2026
BidirectionalBatteryAvailable11.5 MWFlexible, ≤ 10 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
BidirectionalBatteryAvailable11.2 MWFlexible, ≤ 10 % curtailment a year2031 (2031)variant: 70kv26 Sep 2026
BidirectionalBatteryAvailable28.6 MWFlexible, ≤ 20 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
BidirectionalBatteryAvailable27.1 MWFlexible, ≤ 20 % curtailment a year2031 (2031)variant: 70kv26 Sep 2026

Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map

What each value means

Methodology, both clocks, provenance and rights

Injection · Generation (any) · Available

3.9 MW

Granted

The operator's latest published dataset reports 3.9 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/BEERS150 · payload sha256 dc742eb29810…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Generation (any) · Available

1.3 MW

Granted

The operator's latest published dataset reports 1.3 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2027 (2027) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/BEERS 70 · payload sha256 bdbc1dd9b78c…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS 70
Operator note: flexibilityLevel
0%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Generation (any) · Available

7.4 MW

Granted

The operator's latest published dataset reports 7.4 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/BEERS150 · payload sha256 dc742eb29810…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Generation (any) · Available

6.5 MW

Granted

The operator's latest published dataset reports 6.5 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2027 (2027) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/BEERS 70 · payload sha256 bdbc1dd9b78c…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS 70
Operator note: flexibilityLevel
5%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Generation (any) · Available

10 MW

Granted

The operator's latest published dataset reports 10 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/BEERS150 · payload sha256 dc742eb29810…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Generation (any) · Available

9.7 MW

Granted

The operator's latest published dataset reports 9.7 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2027 (2027) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/BEERS 70 · payload sha256 bdbc1dd9b78c…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS 70
Operator note: flexibilityLevel
10%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Generation (any) · Available

21.3 MW

Granted

The operator's latest published dataset reports 21.3 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/BEERS150 · payload sha256 dc742eb29810…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Generation (any) · Available

19.2 MW

Granted

The operator's latest published dataset reports 19.2 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2027 (2027) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/BEERS 70 · payload sha256 bdbc1dd9b78c…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS 70
Operator note: flexibilityLevel
20%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Generation (any) · Available

3.9 MW

Granted

The operator's latest published dataset reports 3.9 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/BEERS150 · payload sha256 e69196bee33f…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Generation (any) · Available

1.3 MW

Granted

The operator's latest published dataset reports 1.3 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2031 (2031) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/BEERS 70 · payload sha256 a9838dbbf166…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS 70
Operator note: flexibilityLevel
0%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Generation (any) · Available

8.6 MW

Granted

The operator's latest published dataset reports 8.6 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/BEERS150 · payload sha256 e69196bee33f…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Generation (any) · Available

6.8 MW

Granted

The operator's latest published dataset reports 6.8 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2031 (2031) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/BEERS 70 · payload sha256 a9838dbbf166…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS 70
Operator note: flexibilityLevel
5%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Generation (any) · Available

11.5 MW

Granted

The operator's latest published dataset reports 11.5 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/BEERS150 · payload sha256 e69196bee33f…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Generation (any) · Available

11.2 MW

Granted

The operator's latest published dataset reports 11.2 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2031 (2031) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/BEERS 70 · payload sha256 a9838dbbf166…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS 70
Operator note: flexibilityLevel
10%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Generation (any) · Available

28.6 MW

Granted

The operator's latest published dataset reports 28.6 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/BEERS150 · payload sha256 e69196bee33f…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Generation (any) · Available

27.1 MW

Granted

The operator's latest published dataset reports 27.1 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2031 (2031) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/BEERS 70 · payload sha256 a9838dbbf166…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS 70
Operator note: flexibilityLevel
20%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Solar PV · Available

6.8 MW

Granted

The operator's latest published dataset reports 6.8 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/BEERS150 · payload sha256 dc742eb29810…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

2 MW

Granted

The operator's latest published dataset reports 2 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2027 (2027) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/BEERS 70 · payload sha256 bdbc1dd9b78c…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS 70
Operator note: flexibilityLevel
0%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Solar PV · Available

12.5 MW

Granted

The operator's latest published dataset reports 12.5 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/BEERS150 · payload sha256 dc742eb29810…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

9.2 MW

Granted

The operator's latest published dataset reports 9.2 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2027 (2027) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/BEERS 70 · payload sha256 bdbc1dd9b78c…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS 70
Operator note: flexibilityLevel
5%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Solar PV · Available

15.9 MW

Granted

The operator's latest published dataset reports 15.9 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/BEERS150 · payload sha256 dc742eb29810…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

12.2 MW

Granted

The operator's latest published dataset reports 12.2 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2027 (2027) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/BEERS 70 · payload sha256 bdbc1dd9b78c…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS 70
Operator note: flexibilityLevel
10%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Solar PV · Available

24.5 MW

Granted

The operator's latest published dataset reports 24.5 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2027 (2027) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/BEERS 70 · payload sha256 bdbc1dd9b78c…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS 70
Operator note: flexibilityLevel
20%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Solar PV · Available

24.5 MW

Granted

The operator's latest published dataset reports 24.5 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/BEERS150 · payload sha256 dc742eb29810…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

6.8 MW

Granted

The operator's latest published dataset reports 6.8 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/BEERS150 · payload sha256 e69196bee33f…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

5 MW

Granted

The operator's latest published dataset reports 5 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2031 (2031) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/BEERS 70 · payload sha256 a9838dbbf166…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS 70
Operator note: flexibilityLevel
0%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Solar PV · Available

12.9 MW

Granted

The operator's latest published dataset reports 12.9 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/BEERS150 · payload sha256 e69196bee33f…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

9.3 MW

Granted

The operator's latest published dataset reports 9.3 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2031 (2031) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/BEERS 70 · payload sha256 a9838dbbf166…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS 70
Operator note: flexibilityLevel
5%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Solar PV · Available

16.3 MW

Granted

The operator's latest published dataset reports 16.3 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/BEERS150 · payload sha256 e69196bee33f…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

12.5 MW

Granted

The operator's latest published dataset reports 12.5 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2031 (2031) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/BEERS 70 · payload sha256 a9838dbbf166…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS 70
Operator note: flexibilityLevel
10%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Solar PV · Available

27.3 MW

Granted

The operator's latest published dataset reports 27.3 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2031 (2031) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/BEERS 70 · payload sha256 a9838dbbf166…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS 70
Operator note: flexibilityLevel
20%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Solar PV · Available

25.4 MW

Granted

The operator's latest published dataset reports 25.4 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/BEERS150 · payload sha256 e69196bee33f…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

5.2 MW

Granted

The operator's latest published dataset reports 5.2 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/BEERS150 · payload sha256 dc742eb29810…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

2.3 MW

Granted

The operator's latest published dataset reports 2.3 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2027 (2027) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/BEERS 70 · payload sha256 bdbc1dd9b78c…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS 70
Operator note: flexibilityLevel
0%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Onshore wind · Available

12 MW

Granted

The operator's latest published dataset reports 12 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2027 (2027) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/BEERS 70 · payload sha256 bdbc1dd9b78c…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS 70
Operator note: flexibilityLevel
5%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Onshore wind · Available

11.3 MW

Granted

The operator's latest published dataset reports 11.3 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/BEERS150 · payload sha256 dc742eb29810…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

18.7 MW

Granted

The operator's latest published dataset reports 18.7 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/BEERS150 · payload sha256 dc742eb29810…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

18.2 MW

Granted

The operator's latest published dataset reports 18.2 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2027 (2027) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/BEERS 70 · payload sha256 bdbc1dd9b78c…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS 70
Operator note: flexibilityLevel
10%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Onshore wind · Available

47.4 MW

Granted

The operator's latest published dataset reports 47.4 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/BEERS150 · payload sha256 dc742eb29810…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

40.9 MW

Granted

The operator's latest published dataset reports 40.9 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2027 (2027) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/BEERS 70 · payload sha256 bdbc1dd9b78c…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS 70
Operator note: flexibilityLevel
20%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Onshore wind · Available

5.3 MW

Granted

The operator's latest published dataset reports 5.3 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/BEERS150 · payload sha256 e69196bee33f…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

2.3 MW

Granted

The operator's latest published dataset reports 2.3 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2031 (2031) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/BEERS 70 · payload sha256 a9838dbbf166…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS 70
Operator note: flexibilityLevel
0%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Onshore wind · Available

14.6 MW

Granted

The operator's latest published dataset reports 14.6 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/BEERS150 · payload sha256 e69196bee33f…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

14.5 MW

Granted

The operator's latest published dataset reports 14.5 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2031 (2031) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/BEERS 70 · payload sha256 a9838dbbf166…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS 70
Operator note: flexibilityLevel
5%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Onshore wind · Available

25.3 MW

Granted

The operator's latest published dataset reports 25.3 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/BEERS150 · payload sha256 e69196bee33f…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

22 MW

Granted

The operator's latest published dataset reports 22 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2031 (2031) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/BEERS 70 · payload sha256 a9838dbbf166…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS 70
Operator note: flexibilityLevel
10%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Injection · Onshore wind · Available

68.5 MW

Granted

The operator's latest published dataset reports 68.5 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/BEERS150 · payload sha256 e69196bee33f…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

60 MW

Granted

The operator's latest published dataset reports 60 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2031 (2031) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/BEERS 70 · payload sha256 a9838dbbf166…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
BEERS 70
Operator note: flexibilityLevel
20%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Offtake · Load (any) · Available

4.1 MW

Granted

The operator's latest published dataset reports 4.1 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/BEERS150 · payload sha256 dc742eb29810…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

1.3 MW

Granted

The operator's latest published dataset reports 1.3 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2027 (2027) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/BEERS 70 · payload sha256 bdbc1dd9b78c…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS 70
Operator note: flexibilityLevel
0%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Offtake · Load (any) · Available

13.7 MW

Granted

The operator's latest published dataset reports 13.7 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/BEERS150 · payload sha256 dc742eb29810…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

3.7 MW

Granted

The operator's latest published dataset reports 3.7 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2027 (2027) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/BEERS 70 · payload sha256 bdbc1dd9b78c…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS 70
Operator note: flexibilityLevel
5%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Offtake · Load (any) · Available

27.4 MW

Granted

The operator's latest published dataset reports 27.4 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2027 (2027) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/BEERS 70 · payload sha256 bdbc1dd9b78c…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS 70
Operator note: flexibilityLevel
10%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Offtake · Load (any) · Available

24.8 MW

Granted

The operator's latest published dataset reports 24.8 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/BEERS150 · payload sha256 dc742eb29810…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

140 MW

Granted

The operator's latest published dataset reports 140 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/BEERS150 · payload sha256 dc742eb29810…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

60 MW

Granted

The operator's latest published dataset reports 60 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2027 (2027) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/BEERS 70 · payload sha256 bdbc1dd9b78c…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
BEERS 70
Operator note: flexibilityLevel
20%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Offtake · Load (any) · Available

4.1 MW

Granted

The operator's latest published dataset reports 4.1 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/BEERS150 · payload sha256 e69196bee33f…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

1.3 MW

Granted

The operator's latest published dataset reports 1.3 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2031 (2031) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/BEERS 70 · payload sha256 a9838dbbf166…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS 70
Operator note: flexibilityLevel
0%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Offtake · Load (any) · Available

90.4 MW

Granted

The operator's latest published dataset reports 90.4 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/BEERS150 · payload sha256 e69196bee33f…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

3.7 MW

Granted

The operator's latest published dataset reports 3.7 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2031 (2031) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/BEERS 70 · payload sha256 a9838dbbf166…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS 70
Operator note: flexibilityLevel
5%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Offtake · Load (any) · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/BEERS150 · payload sha256 e69196bee33f…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
BEERS150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

27.4 MW

Granted

The operator's latest published dataset reports 27.4 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2031 (2031) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/BEERS 70 · payload sha256 a9838dbbf166…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS 70
Operator note: flexibilityLevel
10%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Offtake · Load (any) · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/BEERS150 · payload sha256 e69196bee33f…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
BEERS150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

60 MW

Granted

The operator's latest published dataset reports 60 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2031 (2031) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/BEERS 70 · payload sha256 a9838dbbf166…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
BEERS 70
Operator note: flexibilityLevel
20%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Bidirectional · Battery · Available

3.9 MW

Granted

The operator's latest published dataset reports 3.9 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/BEERS150 · payload sha256 dc742eb29810…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

1.3 MW

Granted

The operator's latest published dataset reports 1.3 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2027 (2027) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/BEERS 70 · payload sha256 bdbc1dd9b78c…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS 70
Operator note: flexibilityLevel
0%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Bidirectional · Battery · Available

7.4 MW

Granted

The operator's latest published dataset reports 7.4 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/BEERS150 · payload sha256 dc742eb29810…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

3.5 MW

Granted

The operator's latest published dataset reports 3.5 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2027 (2027) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/BEERS 70 · payload sha256 bdbc1dd9b78c…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS 70
Operator note: flexibilityLevel
5%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Bidirectional · Battery · Available

10 MW

Granted

The operator's latest published dataset reports 10 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/BEERS150 · payload sha256 dc742eb29810…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

9.7 MW

Granted

The operator's latest published dataset reports 9.7 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2027 (2027) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/BEERS 70 · payload sha256 bdbc1dd9b78c…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS 70
Operator note: flexibilityLevel
10%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Bidirectional · Battery · Available

21.3 MW

Granted

The operator's latest published dataset reports 21.3 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/BEERS150 · payload sha256 dc742eb29810…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

19.2 MW

Granted

The operator's latest published dataset reports 19.2 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2027 (2027) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/BEERS 70 · payload sha256 bdbc1dd9b78c…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS 70
Operator note: flexibilityLevel
20%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Bidirectional · Battery · Available

3.9 MW

Granted

The operator's latest published dataset reports 3.9 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/BEERS150 · payload sha256 e69196bee33f…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

1.3 MW

Granted

The operator's latest published dataset reports 1.3 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2031 (2031) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/BEERS 70 · payload sha256 a9838dbbf166…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS 70
Operator note: flexibilityLevel
0%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Bidirectional · Battery · Available

8.6 MW

Granted

The operator's latest published dataset reports 8.6 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/BEERS150 · payload sha256 e69196bee33f…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

3.5 MW

Granted

The operator's latest published dataset reports 3.5 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2031 (2031) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/BEERS 70 · payload sha256 a9838dbbf166…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS 70
Operator note: flexibilityLevel
5%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Bidirectional · Battery · Available

11.5 MW

Granted

The operator's latest published dataset reports 11.5 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/BEERS150 · payload sha256 e69196bee33f…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

11.2 MW

Granted

The operator's latest published dataset reports 11.2 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2031 (2031) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/BEERS 70 · payload sha256 a9838dbbf166…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS 70
Operator note: flexibilityLevel
10%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

Bidirectional · Battery · Available

28.6 MW

Granted

The operator's latest published dataset reports 28.6 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/BEERS150 · payload sha256 e69196bee33f…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

27.1 MW

Granted

The operator's latest published dataset reports 27.1 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2031 (2031) · variant: 70kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-10-02 07:56 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/BEERS 70 · payload sha256 a9838dbbf166…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
BEERS 70
Operator note: flexibilityLevel
20%_flex
Operator note: variant
70kv
Operator note: voltage kv
70

History

Served series only

Bidirectional · Battery · Available · 2027

current 1.3 MW

26 Sep 2026: 1.3 MW
26 Sep 2026range 1.3 to 1.3 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current1.3 MW

Time axis: when we observed each value, not the operator’s effective date.

Bidirectional · Battery · Available · 2027

current 3.5 MW

26 Sep 2026: 3.5 MW
26 Sep 2026range 3.5 to 3.5 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current3.5 MW

Time axis: when we observed each value, not the operator’s effective date.

Bidirectional · Battery · Available · 2027

current 9.7 MW

26 Sep 2026: 9.7 MW
26 Sep 2026range 9.7 to 9.7 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current9.7 MW

Time axis: when we observed each value, not the operator’s effective date.

Bidirectional · Battery · Available · 2027

current 19.2 MW

26 Sep 2026: 19.2 MW
26 Sep 2026range 19.2 to 19.2 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current19.2 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

current 1.3 MW

26 Sep 2026: 1.3 MW
26 Sep 2026range 1.3 to 1.3 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current1.3 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

current 3.7 MW

26 Sep 2026: 3.7 MW
26 Sep 2026range 3.7 to 3.7 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current3.7 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

current 27.4 MW

26 Sep 2026: 27.4 MW
26 Sep 2026range 27.4 to 27.4 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current27.4 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

current 60 MW

26 Sep 2026: 60 MW
26 Sep 2026range 60 to 60 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current60 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

current 1.3 MW

26 Sep 2026: 1.3 MW
26 Sep 2026range 1.3 to 1.3 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current1.3 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

current 6.5 MW

26 Sep 2026: 6.5 MW
26 Sep 2026range 6.5 to 6.5 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current6.5 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

current 9.7 MW

26 Sep 2026: 9.7 MW
26 Sep 2026range 9.7 to 9.7 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current9.7 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

current 19.2 MW

26 Sep 2026: 19.2 MW
26 Sep 2026range 19.2 to 19.2 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current19.2 MW

Time axis: when we observed each value, not the operator’s effective date.

The first 12 of 80 served series with a history. The history route returns every one of them.

Through the API

curl "https://api.gridcapacityapi.com/v1/substations/sub_06gdrm9m0htr34r50knqzd6wvm/capacity" \  -H "Authorization: Bearer gc_live_..."
BEERS 150 kV substation: grid capacity (Elia Transmission Belgium) · GridCapacity API