| Injection | Generation (any) | Available | 111 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 0 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 175 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 60 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 60 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 60 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 111 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 0 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 175 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 60 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 60 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Generation (any) | Available | 60 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 0 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 60 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 60 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 60 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 0 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 60 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 60 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Solar PV | Available | 60 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 60 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 60 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 60 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 60 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 60 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 60 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 60 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Injection | Onshore wind | Available | 60 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 5.7 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 1.5 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 11.3 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 10.5 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 21.8 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 17.7 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 55.2 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 40.1 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 17.4 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 1.5 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 142 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 60 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 60 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Offtake | Load (any) | Available | 60 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 5.2 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 0 MW | Firm, ≤ 0 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 7.9 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 7.7 MW | Flexible, ≤ 5 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 12.5 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 11.1 MW | Flexible, ≤ 10 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 41.8 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 24.1 MW | Flexible, ≤ 20 % curtailment a year | 2029 (2029)variant: 70kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 6.1 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 0 MW | Firm, ≤ 0 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 110.3 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 24.4 MW | Flexible, ≤ 5 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 175 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 55.4 MW | Flexible, ≤ 10 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 150kv | 17 Nov 2026 |
| Bidirectional | Battery | Available | 60 MW | Flexible, ≤ 20 % curtailment a year | 2033 (2033)variant: 70kv | 17 Nov 2026 |