| Injection | Generation (any) | Available | 4.8 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 1.8 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 36kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 18.9 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 36kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 16.5 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 35 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 36kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 26.8 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 91.9 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 60 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 36kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 4.8 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 1.9 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 36kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 18.9 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 36kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 16.5 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 35 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 36kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 26.8 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 91.9 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Injection | Generation (any) | Available | 60 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 36kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 7.5 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 4.1 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 36kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 60 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 36kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 29.7 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 60 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 36kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 37.1 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 65.6 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 60 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 36kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 7.5 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 4.1 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 36kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 60 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 36kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 29.7 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 60 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 36kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 37.1 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 65.6 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Injection | Solar PV | Available | 60 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 36kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 5.6 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 2.1 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 36kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 23.4 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 36kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 13.9 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 60 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 36kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 29.9 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 130.2 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 60 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 36kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 5.6 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 2.3 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 36kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 23.4 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 36kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 13.9 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 60 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 36kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 29.9 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 130.2 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Injection | Onshore wind | Available | 60 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 36kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 3.5 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 2.3 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 36kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 4.8 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 36kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 4.7 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 5.5 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 36kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 5.2 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 7.4 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 36kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 6.7 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 5.2 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 2.3 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 36kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 12.5 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 9.7 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 36kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 38 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 18.4 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 36kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 175 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Offtake | Load (any) | Available | 54.7 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 36kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 3.5 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 1.8 MW | Firm, ≤ 0 % curtailment a year | 2027 (2027)variant: 36kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 4.7 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 36kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 4.7 MW | Flexible, ≤ 5 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 5.2 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 36kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 5.2 MW | Flexible, ≤ 10 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 6.8 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 36kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 6.6 MW | Flexible, ≤ 20 % curtailment a year | 2027 (2027)variant: 150kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 4.8 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 1.9 MW | Firm, ≤ 0 % curtailment a year | 2031 (2031)variant: 36kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 11.8 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 6.1 MW | Flexible, ≤ 5 % curtailment a year | 2031 (2031)variant: 36kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 26.8 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 10.3 MW | Flexible, ≤ 10 % curtailment a year | 2031 (2031)variant: 36kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 91.9 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 150kv | 26 Sep 2026 |
| Bidirectional | Battery | Available | 36 MW | Flexible, ≤ 20 % curtailment a year | 2031 (2031)variant: 36kv | 26 Sep 2026 |