Substation / 380 kV

ANDUM

Elia Transmission Belgium / Belgium

Latest published values

60 served · 0 withheld

Each row is what the operator’s latest published dataset reports for one combination of direction, technology, measure, firmness and horizon. Hosting-capacity figures are indicative and reflect what operators publish. They are not a connection offer; only the operator can confirm capacity for a specific request.

Latest published capacity values, one row per series
DirectionTechnologyMeasureValueFirmnessHorizonSource date
InjectionGeneration (any)Available14.1 MWFirm, ≤ 0 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionGeneration (any)Available175 MWFlexible, ≤ 5 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionGeneration (any)Available175 MWFlexible, ≤ 10 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionGeneration (any)Available175 MWFlexible, ≤ 20 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionGeneration (any)Available22.1 MWFirm, ≤ 0 % curtailment a year2031 (2031)variant: 380kv26 Sep 2026
InjectionGeneration (any)Available14.1 MWFirm, ≤ 0 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionGeneration (any)Available183.8 MWFlexible, ≤ 5 % curtailment a year2031 (2031)variant: 380kv26 Sep 2026
InjectionGeneration (any)Available175 MWFlexible, ≤ 5 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionGeneration (any)Available270.5 MWFlexible, ≤ 10 % curtailment a year2031 (2031)variant: 380kv17 Oct 2026
InjectionGeneration (any)Available175 MWFlexible, ≤ 10 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionGeneration (any)Available300 MWFlexible, ≤ 20 % curtailment a year2031 (2031)variant: 380kv26 Sep 2026
InjectionGeneration (any)Available175 MWFlexible, ≤ 20 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionSolar PVAvailable39.4 MWFirm, ≤ 0 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionSolar PVAvailable175 MWFlexible, ≤ 5 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionSolar PVAvailable175 MWFlexible, ≤ 10 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionSolar PVAvailable175 MWFlexible, ≤ 20 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionSolar PVAvailable106.4 MWFirm, ≤ 0 % curtailment a year2031 (2031)variant: 380kv26 Sep 2026
InjectionSolar PVAvailable43.2 MWFirm, ≤ 0 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionSolar PVAvailable300 MWFlexible, ≤ 5 % curtailment a year2031 (2031)variant: 380kv26 Sep 2026
InjectionSolar PVAvailable175 MWFlexible, ≤ 5 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionSolar PVAvailable300 MWFlexible, ≤ 10 % curtailment a year2031 (2031)variant: 380kv26 Sep 2026
InjectionSolar PVAvailable175 MWFlexible, ≤ 10 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionSolar PVAvailable300 MWFlexible, ≤ 20 % curtailment a year2031 (2031)variant: 380kv26 Sep 2026
InjectionSolar PVAvailable175 MWFlexible, ≤ 20 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionOnshore windAvailable25.7 MWFirm, ≤ 0 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionOnshore windAvailable175 MWFlexible, ≤ 5 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionOnshore windAvailable175 MWFlexible, ≤ 10 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionOnshore windAvailable175 MWFlexible, ≤ 20 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
InjectionOnshore windAvailable47.7 MWFirm, ≤ 0 % curtailment a year2031 (2031)variant: 380kv17 Oct 2026
InjectionOnshore windAvailable25.7 MWFirm, ≤ 0 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionOnshore windAvailable300 MWFlexible, ≤ 5 % curtailment a year2031 (2031)variant: 380kv26 Sep 2026
InjectionOnshore windAvailable175 MWFlexible, ≤ 5 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionOnshore windAvailable300 MWFlexible, ≤ 10 % curtailment a year2031 (2031)variant: 380kv26 Sep 2026
InjectionOnshore windAvailable175 MWFlexible, ≤ 10 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
InjectionOnshore windAvailable300 MWFlexible, ≤ 20 % curtailment a year2031 (2031)variant: 380kv26 Sep 2026
InjectionOnshore windAvailable175 MWFlexible, ≤ 20 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
OfftakeLoad (any)Available9.2 MWFirm, ≤ 0 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
OfftakeLoad (any)Available18.8 MWFlexible, ≤ 5 % curtailment a year2027 (2027)variant: 150kv17 Oct 2026
OfftakeLoad (any)Available36.6 MWFlexible, ≤ 10 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
OfftakeLoad (any)Available82.4 MWFlexible, ≤ 20 % curtailment a year2027 (2027)variant: 150kv17 Oct 2026
OfftakeLoad (any)Available146.4 MWFirm, ≤ 0 % curtailment a year2031 (2031)variant: 380kv26 Sep 2026
OfftakeLoad (any)Available9.2 MWFirm, ≤ 0 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
OfftakeLoad (any)Available300 MWFlexible, ≤ 5 % curtailment a year2031 (2031)variant: 380kv26 Sep 2026
OfftakeLoad (any)Available18.8 MWFlexible, ≤ 5 % curtailment a year2031 (2031)variant: 150kv17 Oct 2026
OfftakeLoad (any)Available300 MWFlexible, ≤ 10 % curtailment a year2031 (2031)variant: 380kv26 Sep 2026
OfftakeLoad (any)Available46.4 MWFlexible, ≤ 10 % curtailment a year2031 (2031)variant: 150kv17 Oct 2026
OfftakeLoad (any)Available300 MWFlexible, ≤ 20 % curtailment a year2031 (2031)variant: 380kv26 Sep 2026
OfftakeLoad (any)Available175 MWFlexible, ≤ 20 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
BidirectionalBatteryAvailable9.1 MWFirm, ≤ 0 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
BidirectionalBatteryAvailable15.4 MWFlexible, ≤ 5 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
BidirectionalBatteryAvailable32.4 MWFlexible, ≤ 10 % curtailment a year2027 (2027)variant: 150kv26 Sep 2026
BidirectionalBatteryAvailable75.6 MWFlexible, ≤ 20 % curtailment a year2027 (2027)variant: 150kv17 Oct 2026
BidirectionalBatteryAvailable22.1 MWFirm, ≤ 0 % curtailment a year2031 (2031)variant: 380kv26 Sep 2026
BidirectionalBatteryAvailable9.1 MWFirm, ≤ 0 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
BidirectionalBatteryAvailable183.8 MWFlexible, ≤ 5 % curtailment a year2031 (2031)variant: 380kv26 Sep 2026
BidirectionalBatteryAvailable15.4 MWFlexible, ≤ 5 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
BidirectionalBatteryAvailable270.5 MWFlexible, ≤ 10 % curtailment a year2031 (2031)variant: 380kv17 Oct 2026
BidirectionalBatteryAvailable32.4 MWFlexible, ≤ 10 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026
BidirectionalBatteryAvailable300 MWFlexible, ≤ 20 % curtailment a year2031 (2031)variant: 380kv26 Sep 2026
BidirectionalBatteryAvailable175 MWFlexible, ≤ 20 % curtailment a year2031 (2031)variant: 150kv26 Sep 2026

Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map

What each value means

Methodology, both clocks, provenance and rights

Injection · Generation (any) · Available

14.1 MW

Granted

The operator's latest published dataset reports 14.1 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/ANDUM150 · payload sha256 4d9662b33412…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ANDUM150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Generation (any) · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/ANDUM150 · payload sha256 4d9662b33412…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
ANDUM150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Generation (any) · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/ANDUM150 · payload sha256 4d9662b33412…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
ANDUM150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Generation (any) · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/ANDUM150 · payload sha256 4d9662b33412…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
ANDUM150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Generation (any) · Available

22.1 MW

Granted

The operator's latest published dataset reports 22.1 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2031 (2031) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/ANDUM380 · payload sha256 ae98b6adbfff…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ANDUM380
Operator note: flexibilityLevel
0%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Generation (any) · Available

14.1 MW

Granted

The operator's latest published dataset reports 14.1 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/ANDUM150 · payload sha256 e1956e04921e…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ANDUM150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Generation (any) · Available

183.8 MW

Granted

The operator's latest published dataset reports 183.8 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2031 (2031) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/ANDUM380 · payload sha256 ae98b6adbfff…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ANDUM380
Operator note: flexibilityLevel
5%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Generation (any) · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/ANDUM150 · payload sha256 e1956e04921e…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
ANDUM150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Generation (any) · Available

270.5 MW

Granted

The operator's latest published dataset reports 270.5 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2031 (2031) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-10-17 03:28 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/ANDUM380 · payload sha256 55a920f5c7e1…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ANDUM380
Operator note: flexibilityLevel
10%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Generation (any) · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/ANDUM150 · payload sha256 e1956e04921e…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
ANDUM150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Generation (any) · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2031 (2031) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/ANDUM380 · payload sha256 ae98b6adbfff…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
ANDUM380
Operator note: flexibilityLevel
20%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Generation (any) · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/ANDUM150 · payload sha256 e1956e04921e…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
ANDUM150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

39.4 MW

Granted

The operator's latest published dataset reports 39.4 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/ANDUM150 · payload sha256 4d9662b33412…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ANDUM150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/ANDUM150 · payload sha256 4d9662b33412…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
ANDUM150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/ANDUM150 · payload sha256 4d9662b33412…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
ANDUM150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/ANDUM150 · payload sha256 4d9662b33412…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
ANDUM150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

106.4 MW

Granted

The operator's latest published dataset reports 106.4 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2031 (2031) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/ANDUM380 · payload sha256 ae98b6adbfff…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ANDUM380
Operator note: flexibilityLevel
0%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Solar PV · Available

43.2 MW

Granted

The operator's latest published dataset reports 43.2 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/ANDUM150 · payload sha256 e1956e04921e…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ANDUM150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2031 (2031) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/ANDUM380 · payload sha256 ae98b6adbfff…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
ANDUM380
Operator note: flexibilityLevel
5%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Solar PV · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/ANDUM150 · payload sha256 e1956e04921e…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
ANDUM150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2031 (2031) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/ANDUM380 · payload sha256 ae98b6adbfff…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
ANDUM380
Operator note: flexibilityLevel
10%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Solar PV · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/ANDUM150 · payload sha256 e1956e04921e…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
ANDUM150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Solar PV · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2031 (2031) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/ANDUM380 · payload sha256 ae98b6adbfff…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
ANDUM380
Operator note: flexibilityLevel
20%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Solar PV · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/ANDUM150 · payload sha256 e1956e04921e…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
ANDUM150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

25.7 MW

Granted

The operator's latest published dataset reports 25.7 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/ANDUM150 · payload sha256 4d9662b33412…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ANDUM150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/ANDUM150 · payload sha256 4d9662b33412…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
ANDUM150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/ANDUM150 · payload sha256 4d9662b33412…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
ANDUM150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/ANDUM150 · payload sha256 4d9662b33412…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
ANDUM150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

47.7 MW

Granted

The operator's latest published dataset reports 47.7 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2031 (2031) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-10-17 03:28 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/ANDUM380 · payload sha256 55a920f5c7e1…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ANDUM380
Operator note: flexibilityLevel
0%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Onshore wind · Available

25.7 MW

Granted

The operator's latest published dataset reports 25.7 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/ANDUM150 · payload sha256 e1956e04921e…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ANDUM150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2031 (2031) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/ANDUM380 · payload sha256 ae98b6adbfff…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
ANDUM380
Operator note: flexibilityLevel
5%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Onshore wind · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/ANDUM150 · payload sha256 e1956e04921e…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
ANDUM150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2031 (2031) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/ANDUM380 · payload sha256 ae98b6adbfff…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
ANDUM380
Operator note: flexibilityLevel
10%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Onshore wind · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/ANDUM150 · payload sha256 e1956e04921e…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
ANDUM150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Injection · Onshore wind · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2031 (2031) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/ANDUM380 · payload sha256 ae98b6adbfff…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
ANDUM380
Operator note: flexibilityLevel
20%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Injection · Onshore wind · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/ANDUM150 · payload sha256 e1956e04921e…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
ANDUM150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

9.2 MW

Granted

The operator's latest published dataset reports 9.2 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/ANDUM150 · payload sha256 4d9662b33412…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ANDUM150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

18.8 MW

Granted

The operator's latest published dataset reports 18.8 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-10-17 03:28 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/ANDUM150 · payload sha256 57ec39d2f0f5…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ANDUM150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

36.6 MW

Granted

The operator's latest published dataset reports 36.6 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/ANDUM150 · payload sha256 4d9662b33412…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ANDUM150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

82.4 MW

Granted

The operator's latest published dataset reports 82.4 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-10-17 03:28 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/ANDUM150 · payload sha256 57ec39d2f0f5…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ANDUM150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

146.4 MW

Granted

The operator's latest published dataset reports 146.4 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2031 (2031) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/ANDUM380 · payload sha256 ae98b6adbfff…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ANDUM380
Operator note: flexibilityLevel
0%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Offtake · Load (any) · Available

9.2 MW

Granted

The operator's latest published dataset reports 9.2 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/ANDUM150 · payload sha256 e1956e04921e…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ANDUM150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2031 (2031) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/ANDUM380 · payload sha256 ae98b6adbfff…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
ANDUM380
Operator note: flexibilityLevel
5%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Offtake · Load (any) · Available

18.8 MW

Granted

The operator's latest published dataset reports 18.8 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-10-17 03:28 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/ANDUM150 · payload sha256 3dba2885fa84…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ANDUM150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2031 (2031) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/ANDUM380 · payload sha256 ae98b6adbfff…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
ANDUM380
Operator note: flexibilityLevel
10%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Offtake · Load (any) · Available

46.4 MW

Granted

The operator's latest published dataset reports 46.4 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-10-17 03:28 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/ANDUM150 · payload sha256 3dba2885fa84…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ANDUM150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Offtake · Load (any) · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2031 (2031) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/ANDUM380 · payload sha256 ae98b6adbfff…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
ANDUM380
Operator note: flexibilityLevel
20%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Offtake · Load (any) · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/ANDUM150 · payload sha256 e1956e04921e…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
ANDUM150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

9.1 MW

Granted

The operator's latest published dataset reports 9.1 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/ANDUM150 · payload sha256 4d9662b33412…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ANDUM150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

15.4 MW

Granted

The operator's latest published dataset reports 15.4 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/ANDUM150 · payload sha256 4d9662b33412…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ANDUM150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

32.4 MW

Granted

The operator's latest published dataset reports 32.4 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/ANDUM150 · payload sha256 4d9662b33412…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ANDUM150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

75.6 MW

Granted

The operator's latest published dataset reports 75.6 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2027 (2027) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-10-17 03:28 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2027/ANDUM150 · payload sha256 57ec39d2f0f5…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ANDUM150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

22.1 MW

Granted

The operator's latest published dataset reports 22.1 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2031 (2031) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/ANDUM380 · payload sha256 ae98b6adbfff…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ANDUM380
Operator note: flexibilityLevel
0%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Bidirectional · Battery · Available

9.1 MW

Granted

The operator's latest published dataset reports 9.1 MW under methodology be_elia_hcm_v2.

Firmness
Firm, ≤ 0 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/ANDUM150 · payload sha256 e1956e04921e…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ANDUM150
Operator note: flexibilityLevel
0%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

183.8 MW

Granted

The operator's latest published dataset reports 183.8 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2031 (2031) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/ANDUM380 · payload sha256 ae98b6adbfff…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ANDUM380
Operator note: flexibilityLevel
5%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Bidirectional · Battery · Available

15.4 MW

Granted

The operator's latest published dataset reports 15.4 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 5 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/ANDUM150 · payload sha256 e1956e04921e…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ANDUM150
Operator note: flexibilityLevel
5%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

270.5 MW

Granted

The operator's latest published dataset reports 270.5 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2031 (2031) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-10-17 03:28 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/ANDUM380 · payload sha256 55a920f5c7e1…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ANDUM380
Operator note: flexibilityLevel
10%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Bidirectional · Battery · Available

32.4 MW

Granted

The operator's latest published dataset reports 32.4 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 10 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/ANDUM150 · payload sha256 e1956e04921e…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: code
ANDUM150
Operator note: flexibilityLevel
10%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

Bidirectional · Battery · Available

300 MW

Granted

The operator's latest published dataset reports 300 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2031 (2031) · variant: 380kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/ANDUM380 · payload sha256 ae98b6adbfff…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at published maximum mw
300
Operator note: at voltage level cap
true
Operator note: code
ANDUM380
Operator note: flexibilityLevel
20%_flex
Operator note: variant
380kv
Operator note: voltage kv
380

Bidirectional · Battery · Available

175 MW

Granted

The operator's latest published dataset reports 175 MW under methodology be_elia_hcm_v2.

Firmness
Flexible, ≤ 20 % curtailment a year
Horizon
2031 (2031) · variant: 150kv
Methodology
be_elia_hcm_v2Elia Grid Hosting Capacity: remaining available capacity per node, profile and flexibility levelbasis operator calculated · network state n and n minus 1 · comparability class be_elia_hcm_v2Not additive across assets. The method accounts for reserved: yes · allocated: yes · pre-reserved: yes · pending requests: not stated
Operator’s date
Not stated by the operator
Retrieved / confirmed
2026-09-26 06:04 UTClast confirmed unchanged 2026-11-11 01:35 UTC
Source health
Healthy
Provenance
be_elia_hosting_capacityrecord 2031/ANDUM150 · payload sha256 e1956e04921e…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Source: Elia Transmission Belgium SA, Grid Hosting Capacity Map
Decision context
Not binding · indicative · a formal connection study is required
Operator note: at voltage level cap
true
Operator note: code
ANDUM150
Operator note: flexibilityLevel
20%_flex
Operator note: variant
150kv
Operator note: voltage kv
150

History

Served series only

Bidirectional · Battery · Available · 2027

current 9.1 MW

26 Sep 2026: 9.1 MW
26 Sep 2026range 9.1 to 9.1 MW11 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current9.1 MW

Time axis: when we observed each value, not the operator’s effective date.

Bidirectional · Battery · Available · 2027

current 15.4 MW

26 Sep 2026: 15.4 MW
26 Sep 2026range 15.4 to 15.4 MW11 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current15.4 MW

Time axis: when we observed each value, not the operator’s effective date.

Bidirectional · Battery · Available · 2027

current 32.4 MW

26 Sep 2026: 32.4 MW
26 Sep 2026range 32.4 to 32.4 MW11 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current32.4 MW

Time axis: when we observed each value, not the operator’s effective date.

Bidirectional · Battery · Available · 2027

current 75.6 MW

26 Sep 2026: 75.7 MW17 Oct 2026: 75.6 MW
26 Sep 2026range 75.6 to 75.7 MW11 Nov 2026
2 published values, as a table
Observed fromUntilValue
26 Sep 202617 Oct 202675.7 MW
17 Oct 2026current75.6 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

current 9.2 MW

26 Sep 2026: 9.2 MW
26 Sep 2026range 9.2 to 9.2 MW11 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current9.2 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

current 18.8 MW

26 Sep 2026: 21.1 MW17 Oct 2026: 18.8 MW
26 Sep 2026range 18.8 to 21.1 MW11 Nov 2026
2 published values, as a table
Observed fromUntilValue
26 Sep 202617 Oct 202621.1 MW
17 Oct 2026current18.8 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

current 36.6 MW

26 Sep 2026: 36.6 MW
26 Sep 2026range 36.6 to 36.6 MW11 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current36.6 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available · 2027

current 82.4 MW

26 Sep 2026: 82.6 MW17 Oct 2026: 82.4 MW
26 Sep 2026range 82.4 to 82.6 MW11 Nov 2026
2 published values, as a table
Observed fromUntilValue
26 Sep 202617 Oct 202682.6 MW
17 Oct 2026current82.4 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

current 14.1 MW

26 Sep 2026: 14.1 MW
26 Sep 2026range 14.1 to 14.1 MW11 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current14.1 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

current 175 MW

26 Sep 2026: 175 MW
26 Sep 2026range 175 to 175 MW11 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current175 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

current 175 MW

26 Sep 2026: 175 MW
26 Sep 2026range 175 to 175 MW11 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current175 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Available · 2027

current 175 MW

26 Sep 2026: 175 MW
26 Sep 2026range 175 to 175 MW11 Nov 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current175 MW

Time axis: when we observed each value, not the operator’s effective date.

The first 12 of 60 served series with a history. The history route returns every one of them.

Through the API

curl "https://api.gridcapacityapi.com/v1/substations/sub_06gdrm9kz5sb5b8qxvq45fkat0/capacity" \  -H "Authorization: Bearer gc_live_..."