Busbar / 20 kV

ST ALZIRA (ALCI)

i-DE Redes Eléctricas Inteligentes, S.A.U. / Alzira, Valencia/València, Spain

Latest published values

3 served · 0 withheld

Each row is what the operator’s latest published dataset reports for one combination of direction, technology, measure, firmness and horizon. Hosting-capacity figures are indicative and reflect what operators publish. They are not a connection offer; only the operator can confirm capacity for a specific request.

Latest published capacity values, one row per series
DirectionTechnologyMeasureValueFirmnessHorizonSource date
InjectionGeneration (any)Allocated5.85 MWUnknownNow (snapshot)11 Nov 2026
InjectionGeneration (any)Available15.74 MWUnknownNow (snapshot)11 Nov 2026
InjectionGeneration (any)Requested0.75 MWUnknownNow (snapshot)11 Nov 2026

Origen de los datos: Comisión Nacional de los Mercados y la Competencia (CNMC) (last updated 2026-11-11)

What each value means

Methodology, both clocks, provenance and rights

Injection · Generation (any) · Allocated

5.85 MW

Granted

The operator's latest published dataset reports 5.85 MW under methodology es_cnmc_gen_rdd_2026.

Firmness
Unknown
Horizon
Now (snapshot)
Methodology
es_cnmc_gen_rdd_2026Generation access capacity at the distribution networks (each DSO's figures in CNMC's map)basis operator calculated · network state unknown · comparability class es_rdd_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
11 Nov 2026
Retrieved / confirmed
2026-11-12 01:53 UTClast confirmed unchanged 2026-11-22 13:05 UTC
Source health
Healthy
Provenance
es_cnmc_generation_capacityrecord rdd:R1-001:ST ALZIRA (ALCI):20#2 · payload sha256 0206fc835996…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Origen de los datos: Comisión Nacional de los Mercados y la Competencia (CNMC) (last updated 2026-11-11)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
CAP_OCUPADA

Injection · Generation (any) · Available

15.74 MW

Granted

The operator's latest published dataset reports 15.74 MW under methodology es_cnmc_gen_rdd_2026.

Firmness
Unknown
Horizon
Now (snapshot)
Methodology
es_cnmc_gen_rdd_2026Generation access capacity at the distribution networks (each DSO's figures in CNMC's map)basis operator calculated · network state unknown · comparability class es_rdd_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
11 Nov 2026
Retrieved / confirmed
2026-11-12 01:53 UTClast confirmed unchanged 2026-11-22 13:05 UTC
Source health
Healthy
Provenance
es_cnmc_generation_capacityrecord rdd:R1-001:ST ALZIRA (ALCI):20#2 · payload sha256 0206fc835996…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Origen de los datos: Comisión Nacional de los Mercados y la Competencia (CNMC) (last updated 2026-11-11)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: regulatory reservation
true
Operator note: source field
CAP_DISPONIBLE

Injection · Generation (any) · Requested

0.75 MW

Granted

The operator's latest published dataset reports 0.75 MW under methodology es_cnmc_gen_rdd_2026.

Firmness
Unknown
Horizon
Now (snapshot)
Methodology
es_cnmc_gen_rdd_2026Generation access capacity at the distribution networks (each DSO's figures in CNMC's map)basis operator calculated · network state unknown · comparability class es_rdd_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
11 Nov 2026
Retrieved / confirmed
2026-11-12 01:53 UTClast confirmed unchanged 2026-11-22 13:05 UTC
Source health
Healthy
Provenance
es_cnmc_generation_capacityrecord rdd:R1-001:ST ALZIRA (ALCI):20#2 · payload sha256 0206fc835996…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Origen de los datos: Comisión Nacional de los Mercados y la Competencia (CNMC) (last updated 2026-11-11)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
CAP_ADMITIDA_NO_RESUELTA

History

Served series only

Injection · Generation (any) · Available

current 15.74 MW

26 Sep 2026: 16.41 MW12 Nov 2026: 15.74 MW
26 Sep 2026range 15.74 to 16.41 MW24 Nov 2026
2 published values, as a table
Observed fromUntilValue
26 Sep 202612 Nov 202616.41 MW
12 Nov 2026current15.74 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Allocated

current 5.85 MW

26 Sep 2026: 5.1 MW12 Nov 2026: 5.85 MW
26 Sep 2026range 5.1 to 5.85 MW24 Nov 2026
2 published values, as a table
Observed fromUntilValue
26 Sep 202612 Nov 20265.1 MW
12 Nov 2026current5.85 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Requested

current 0.75 MW

26 Sep 2026: 0 MW12 Nov 2026: 0.75 MW
26 Sep 2026range 0 to 0.75 MW24 Nov 2026
2 published values, as a table
Observed fromUntilValue
26 Sep 202612 Nov 20260 MW
12 Nov 2026current0.75 MW

Time axis: when we observed each value, not the operator’s effective date.

Through the API

curl "https://api.gridcapacityapi.com/v1/grid-assets/bus_06gdrjgzm1t0sbj09ft453gv70/capacity" \  -H "Authorization: Bearer gc_live_..."