Skip to content

Busbar / 20 kV

B_AIRES

Edistribución Redes Digitales, S.L.U. / Santa Cruz de Tenerife, Santa Cruz de Tenerife, Spain

Latest published values

3 served · 0 withheld

Each row is what the operator’s latest published dataset reports for one combination of direction, technology, measure, firmness and horizon. Hosting-capacity figures are indicative and reflect what operators publish. They are not a connection offer; only the operator can confirm capacity for a specific request.

Latest published capacity values, one row per series
DirectionTechnologyMeasureValueFirmnessHorizonSource date
InjectionGeneration (any)Allocated23.95 MWUnknownNow (snapshot)9 Sep 2026
InjectionGeneration (any)Available88.82 MWUnknownNow (snapshot)9 Sep 2026
InjectionGeneration (any)Requested0.1 MWUnknownNow (snapshot)9 Sep 2026

Origen de los datos: Comisión Nacional de los Mercados y la Competencia (CNMC) (last updated 2026-09-09)

What each value means

Methodology, both clocks, provenance and rights

Injection · Generation (any) · Allocated

23.95 MW

Granted

The operator's latest published dataset reports 23.95 MW under methodology es_cnmc_gen_rdd_2026.

Firmness
Unknown
Horizon
Now (snapshot)
Methodology
es_cnmc_gen_rdd_2026Generation access capacity at the distribution networks (each DSO's figures in CNMC's map)basis operator calculated · network state unknown · comparability class es_rdd_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
9 Sep 2026
Retrieved / confirmed
2026-09-26 05:57 UTClast confirmed unchanged 2026-10-02 07:46 UTC
Source health
Healthy
Provenance
es_cnmc_generation_capacityrecord rdd:R1-299:B_AIRES:20 · payload sha256 f9152ca5c346…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Origen de los datos: Comisión Nacional de los Mercados y la Competencia (CNMC) (last updated 2026-09-09)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
CAP_OCUPADA

Injection · Generation (any) · Available

88.82 MW

Granted

The operator's latest published dataset reports 88.82 MW under methodology es_cnmc_gen_rdd_2026.

Firmness
Unknown
Horizon
Now (snapshot)
Methodology
es_cnmc_gen_rdd_2026Generation access capacity at the distribution networks (each DSO's figures in CNMC's map)basis operator calculated · network state unknown · comparability class es_rdd_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
9 Sep 2026
Retrieved / confirmed
2026-09-26 05:57 UTClast confirmed unchanged 2026-10-02 07:46 UTC
Source health
Healthy
Provenance
es_cnmc_generation_capacityrecord rdd:R1-299:B_AIRES:20 · payload sha256 f9152ca5c346…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Origen de los datos: Comisión Nacional de los Mercados y la Competencia (CNMC) (last updated 2026-09-09)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: limited by short circuit power
true
Operator note: source field
CAP_DISPONIBLE

Injection · Generation (any) · Requested

0.1 MW

Granted

The operator's latest published dataset reports 0.1 MW under methodology es_cnmc_gen_rdd_2026.

Firmness
Unknown
Horizon
Now (snapshot)
Methodology
es_cnmc_gen_rdd_2026Generation access capacity at the distribution networks (each DSO's figures in CNMC's map)basis operator calculated · network state unknown · comparability class es_rdd_generation_access_cir1_2021Not additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
9 Sep 2026
Retrieved / confirmed
2026-09-26 05:57 UTClast confirmed unchanged 2026-10-02 07:46 UTC
Source health
Healthy
Provenance
es_cnmc_generation_capacityrecord rdd:R1-299:B_AIRES:20 · payload sha256 f9152ca5c346…Operator’s publication (opens the operator’s site)
Licence
Permission by telephone, reported by the owner on 2026-10-02Attribution: Origen de los datos: Comisión Nacional de los Mercados y la Competencia (CNMC) (last updated 2026-09-09)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: source field
CAP_ADMITIDA_NO_RESUELTA

History

Served series only

Injection · Generation (any) · Available

current 88.82 MW

26 Sep 2026: 88.82 MW
26 Sep 2026range 88.82 to 88.82 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current88.82 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Allocated

current 23.95 MW

26 Sep 2026: 23.95 MW
26 Sep 2026range 23.95 to 23.95 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current23.95 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Generation (any) · Requested

current 0.1 MW

26 Sep 2026: 0.1 MW
26 Sep 2026range 0.1 to 0.1 MW2 Oct 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0.1 MW

Time axis: when we observed each value, not the operator’s effective date.

Through the API

curl "https://api.gridcapacityapi.com/v1/grid-assets/bus_06gdrjgzm5s211fk4wgsbv4bgc/capacity" \  -H "Authorization: Bearer gc_live_..."
B_AIRES 20 kV busbar: grid capacity (Edistribución Redes Digitales, S.L.U.) · GridCapacity API