Skip to content
GridCapacityAPI.com

Substation · 132 kV · transmission

Rislev

Energinet · Denmark

Latest published values

44 served · 0 withheld

Each row is what the operator’s latest published dataset reports for one combination of direction, technology, measure, firmness and horizon. Hosting-capacity figures are indicative and reflect what operators publish. They are not a connection offer; only the operator can confirm capacity for a specific request.

Latest published capacity values, one row per series
DirectionTechnologyMeasureValueFirmnessHorizonSource date
InjectionGeneration (any)Available930 MWUnknownNow (snapshot)variant: reinforced_grid1 Feb 2026
InjectionGeneration (any)Available696 MWUnknownNow (snapshot)variant: existing_grid1 Feb 2026
InjectionUnknownAvailable47%UnknownNow (snapshot)variant: existing_grid:solar_100mw1 Feb 2026
InjectionUnknownAvailable45%UnknownNow (snapshot)variant: existing_grid:solar_300mw1 Feb 2026
InjectionUnknownAvailable90%UnknownNow (snapshot)variant: existing_grid:wind_100mw1 Feb 2026
InjectionUnknownAvailable89%UnknownNow (snapshot)variant: existing_grid:wind_300mw1 Feb 2026
InjectionUnknownAvailable81%UnknownNow (snapshot)variant: reinforced_grid:solar_100mw1 Feb 2026
InjectionUnknownAvailable77%UnknownNow (snapshot)variant: reinforced_grid:solar_300mw1 Feb 2026
InjectionUnknownAvailable96%UnknownNow (snapshot)variant: reinforced_grid:wind_100mw1 Feb 2026
InjectionUnknownAvailable96%UnknownNow (snapshot)variant: reinforced_grid:wind_300mw1 Feb 2026
OfftakeLoad (any)Available0 MWUnknownNow (snapshot)variant: existing_grid1 Feb 2026
OfftakeLoad (any)Available0 MWUnknownNow (snapshot)variant: reinforced_grid1 Feb 2026
OfftakeLoad (any)Available0%UnknownNow (snapshot)season: summer · variant: existing_grid:0006_100mw1 Feb 2026
OfftakeLoad (any)Available0%UnknownNow (snapshot)season: summer · variant: existing_grid:0006_300mw1 Feb 2026
OfftakeLoad (any)Available0%UnknownNow (snapshot)season: summer · variant: existing_grid:0617_100mw1 Feb 2026
OfftakeLoad (any)Available0%UnknownNow (snapshot)season: summer · variant: existing_grid:0617_300mw1 Feb 2026
OfftakeLoad (any)Available0%UnknownNow (snapshot)season: summer · variant: existing_grid:1721_100mw1 Feb 2026
OfftakeLoad (any)Available0%UnknownNow (snapshot)season: summer · variant: existing_grid:1721_300mw1 Feb 2026
OfftakeLoad (any)Available0%UnknownNow (snapshot)season: summer · variant: existing_grid:2100_100mw1 Feb 2026
OfftakeLoad (any)Available0%UnknownNow (snapshot)season: summer · variant: existing_grid:2100_300mw1 Feb 2026
OfftakeLoad (any)Available0%UnknownNow (snapshot)season: winter · variant: existing_grid:0006_100mw1 Feb 2026
OfftakeLoad (any)Available0%UnknownNow (snapshot)season: winter · variant: existing_grid:0006_300mw1 Feb 2026
OfftakeLoad (any)Available0%UnknownNow (snapshot)season: winter · variant: existing_grid:0617_100mw1 Feb 2026
OfftakeLoad (any)Available0%UnknownNow (snapshot)season: winter · variant: existing_grid:0617_300mw1 Feb 2026
OfftakeLoad (any)Available0%UnknownNow (snapshot)season: winter · variant: existing_grid:1721_100mw1 Feb 2026
OfftakeLoad (any)Available0%UnknownNow (snapshot)season: winter · variant: existing_grid:1721_300mw1 Feb 2026
OfftakeLoad (any)Available0%UnknownNow (snapshot)season: winter · variant: existing_grid:2100_100mw1 Feb 2026
OfftakeLoad (any)Available0%UnknownNow (snapshot)season: winter · variant: existing_grid:2100_300mw1 Feb 2026
OfftakeLoad (any)Available0%UnknownNow (snapshot)season: summer · variant: reinforced_grid:0006_100mw1 Feb 2026
OfftakeLoad (any)Available0%UnknownNow (snapshot)season: summer · variant: reinforced_grid:0006_300mw1 Feb 2026
OfftakeLoad (any)Available0%UnknownNow (snapshot)season: summer · variant: reinforced_grid:0617_100mw1 Feb 2026
OfftakeLoad (any)Available0%UnknownNow (snapshot)season: summer · variant: reinforced_grid:0617_300mw1 Feb 2026
OfftakeLoad (any)Available0%UnknownNow (snapshot)season: summer · variant: reinforced_grid:1721_100mw1 Feb 2026
OfftakeLoad (any)Available0%UnknownNow (snapshot)season: summer · variant: reinforced_grid:1721_300mw1 Feb 2026
OfftakeLoad (any)Available0%UnknownNow (snapshot)season: summer · variant: reinforced_grid:2100_100mw1 Feb 2026
OfftakeLoad (any)Available0%UnknownNow (snapshot)season: summer · variant: reinforced_grid:2100_300mw1 Feb 2026
OfftakeLoad (any)Available0%UnknownNow (snapshot)season: winter · variant: reinforced_grid:0006_100mw1 Feb 2026
OfftakeLoad (any)Available0%UnknownNow (snapshot)season: winter · variant: reinforced_grid:0006_300mw1 Feb 2026
OfftakeLoad (any)Available0%UnknownNow (snapshot)season: winter · variant: reinforced_grid:0617_100mw1 Feb 2026
OfftakeLoad (any)Available0%UnknownNow (snapshot)season: winter · variant: reinforced_grid:0617_300mw1 Feb 2026
OfftakeLoad (any)Available0%UnknownNow (snapshot)season: winter · variant: reinforced_grid:1721_100mw1 Feb 2026
OfftakeLoad (any)Available0%UnknownNow (snapshot)season: winter · variant: reinforced_grid:1721_300mw1 Feb 2026
OfftakeLoad (any)Available0%UnknownNow (snapshot)season: winter · variant: reinforced_grid:2100_100mw1 Feb 2026
OfftakeLoad (any)Available0%UnknownNow (snapshot)season: winter · variant: reinforced_grid:2100_300mw1 Feb 2026

Source: Energinet (www.energidataservice.dk) (last updated 2026-02-01)

What each value means

Methodology, both clocks, provenance and rights

Injection · Generation (any) · Available

930 MW

Granted

The operator's latest published dataset reports 930 MW under methodology dk_energinet_tso_capacity_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: reinforced_grid
Methodology
dk_energinet_tso_capacity_2026Energinet transmission-station connection capacitybasis operator calculated · network state unknown · comparability class dk_energinet_tso_capacityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Feb 2026
Retrieved / confirmed
2026-09-26 05:56 UTClast confirmed unchanged 2026-09-26 05:56 UTC
Source health
Stale
Provenance
dk_energinet_tso_capacityrecord RIL_132:reinforced_grid · payload sha256 2fe98e85b9ca…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: Source: Energinet (www.energidataservice.dk) (last updated 2026-02-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: grid precondition
reinforced_grid
Operator note: source field
available_capacity_production_MW

Injection · Generation (any) · Available

696 MW

Granted

The operator's latest published dataset reports 696 MW under methodology dk_energinet_tso_capacity_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: existing_grid
Methodology
dk_energinet_tso_capacity_2026Energinet transmission-station connection capacitybasis operator calculated · network state unknown · comparability class dk_energinet_tso_capacityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Feb 2026
Retrieved / confirmed
2026-09-26 05:56 UTClast confirmed unchanged 2026-09-26 05:56 UTC
Source health
Stale
Provenance
dk_energinet_tso_capacityrecord RIL_132:existing_grid · payload sha256 ab96563d2e47…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: Source: Energinet (www.energidataservice.dk) (last updated 2026-02-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: grid precondition
existing_grid
Operator note: source field
available_capacity_production_MW

Injection · Unknown · Available

47%

Published in percent; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 47 percent under methodology dk_energinet_tso_capacity_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: existing_grid:solar_100mw
Methodology
dk_energinet_tso_capacity_2026Energinet transmission-station connection capacitybasis operator calculated · network state unknown · comparability class dk_energinet_tso_capacityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Feb 2026
Retrieved / confirmed
2026-09-26 05:56 UTClast confirmed unchanged 2026-09-26 05:56 UTC
Source health
Stale
Provenance
dk_energinet_tso_capacityrecord RIL_132:existing_grid · payload sha256 ab96563d2e47…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: Source: Energinet (www.energidataservice.dk) (last updated 2026-02-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: grid precondition
existing_grid
Operator note: measure
share of a typical year's production that a plant of this size could deliver
Operator note: plant size mw
100
Operator note: source field
cap_solar_100MW_pct
Operator note: technology label
solar

Injection · Unknown · Available

45%

Published in percent; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 45 percent under methodology dk_energinet_tso_capacity_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: existing_grid:solar_300mw
Methodology
dk_energinet_tso_capacity_2026Energinet transmission-station connection capacitybasis operator calculated · network state unknown · comparability class dk_energinet_tso_capacityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Feb 2026
Retrieved / confirmed
2026-09-26 05:56 UTClast confirmed unchanged 2026-09-26 05:56 UTC
Source health
Stale
Provenance
dk_energinet_tso_capacityrecord RIL_132:existing_grid · payload sha256 ab96563d2e47…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: Source: Energinet (www.energidataservice.dk) (last updated 2026-02-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: grid precondition
existing_grid
Operator note: measure
share of a typical year's production that a plant of this size could deliver
Operator note: plant size mw
300
Operator note: source field
cap_solar_300MW_pct
Operator note: technology label
solar

Injection · Unknown · Available

90%

Published in percent; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 90 percent under methodology dk_energinet_tso_capacity_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: existing_grid:wind_100mw
Methodology
dk_energinet_tso_capacity_2026Energinet transmission-station connection capacitybasis operator calculated · network state unknown · comparability class dk_energinet_tso_capacityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Feb 2026
Retrieved / confirmed
2026-09-26 05:56 UTClast confirmed unchanged 2026-09-26 05:56 UTC
Source health
Stale
Provenance
dk_energinet_tso_capacityrecord RIL_132:existing_grid · payload sha256 ab96563d2e47…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: Source: Energinet (www.energidataservice.dk) (last updated 2026-02-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: grid precondition
existing_grid
Operator note: measure
share of a typical year's production that a plant of this size could deliver
Operator note: plant size mw
100
Operator note: source field
cap_wind_100MW_pct
Operator note: technology label
wind

Injection · Unknown · Available

89%

Published in percent; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 89 percent under methodology dk_energinet_tso_capacity_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: existing_grid:wind_300mw
Methodology
dk_energinet_tso_capacity_2026Energinet transmission-station connection capacitybasis operator calculated · network state unknown · comparability class dk_energinet_tso_capacityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Feb 2026
Retrieved / confirmed
2026-09-26 05:56 UTClast confirmed unchanged 2026-09-26 05:56 UTC
Source health
Stale
Provenance
dk_energinet_tso_capacityrecord RIL_132:existing_grid · payload sha256 ab96563d2e47…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: Source: Energinet (www.energidataservice.dk) (last updated 2026-02-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: grid precondition
existing_grid
Operator note: measure
share of a typical year's production that a plant of this size could deliver
Operator note: plant size mw
300
Operator note: source field
cap_wind_300MW_pct
Operator note: technology label
wind

Injection · Unknown · Available

81%

Published in percent; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 81 percent under methodology dk_energinet_tso_capacity_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: reinforced_grid:solar_100mw
Methodology
dk_energinet_tso_capacity_2026Energinet transmission-station connection capacitybasis operator calculated · network state unknown · comparability class dk_energinet_tso_capacityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Feb 2026
Retrieved / confirmed
2026-09-26 05:56 UTClast confirmed unchanged 2026-09-26 05:56 UTC
Source health
Stale
Provenance
dk_energinet_tso_capacityrecord RIL_132:reinforced_grid · payload sha256 2fe98e85b9ca…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: Source: Energinet (www.energidataservice.dk) (last updated 2026-02-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: grid precondition
reinforced_grid
Operator note: measure
share of a typical year's production that a plant of this size could deliver
Operator note: plant size mw
100
Operator note: source field
cap_solar_100MW_pct
Operator note: technology label
solar

Injection · Unknown · Available

77%

Published in percent; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 77 percent under methodology dk_energinet_tso_capacity_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: reinforced_grid:solar_300mw
Methodology
dk_energinet_tso_capacity_2026Energinet transmission-station connection capacitybasis operator calculated · network state unknown · comparability class dk_energinet_tso_capacityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Feb 2026
Retrieved / confirmed
2026-09-26 05:56 UTClast confirmed unchanged 2026-09-26 05:56 UTC
Source health
Stale
Provenance
dk_energinet_tso_capacityrecord RIL_132:reinforced_grid · payload sha256 2fe98e85b9ca…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: Source: Energinet (www.energidataservice.dk) (last updated 2026-02-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: grid precondition
reinforced_grid
Operator note: measure
share of a typical year's production that a plant of this size could deliver
Operator note: plant size mw
300
Operator note: source field
cap_solar_300MW_pct
Operator note: technology label
solar

Injection · Unknown · Available

96%

Published in percent; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 96 percent under methodology dk_energinet_tso_capacity_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: reinforced_grid:wind_100mw
Methodology
dk_energinet_tso_capacity_2026Energinet transmission-station connection capacitybasis operator calculated · network state unknown · comparability class dk_energinet_tso_capacityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Feb 2026
Retrieved / confirmed
2026-09-26 05:56 UTClast confirmed unchanged 2026-09-26 05:56 UTC
Source health
Stale
Provenance
dk_energinet_tso_capacityrecord RIL_132:reinforced_grid · payload sha256 2fe98e85b9ca…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: Source: Energinet (www.energidataservice.dk) (last updated 2026-02-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: grid precondition
reinforced_grid
Operator note: measure
share of a typical year's production that a plant of this size could deliver
Operator note: plant size mw
100
Operator note: source field
cap_wind_100MW_pct
Operator note: technology label
wind

Injection · Unknown · Available

96%

Published in percent; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 96 percent under methodology dk_energinet_tso_capacity_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: reinforced_grid:wind_300mw
Methodology
dk_energinet_tso_capacity_2026Energinet transmission-station connection capacitybasis operator calculated · network state unknown · comparability class dk_energinet_tso_capacityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Feb 2026
Retrieved / confirmed
2026-09-26 05:56 UTClast confirmed unchanged 2026-09-26 05:56 UTC
Source health
Stale
Provenance
dk_energinet_tso_capacityrecord RIL_132:reinforced_grid · payload sha256 2fe98e85b9ca…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: Source: Energinet (www.energidataservice.dk) (last updated 2026-02-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: grid precondition
reinforced_grid
Operator note: measure
share of a typical year's production that a plant of this size could deliver
Operator note: plant size mw
300
Operator note: source field
cap_wind_300MW_pct
Operator note: technology label
wind

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology dk_energinet_tso_capacity_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: existing_grid
Methodology
dk_energinet_tso_capacity_2026Energinet transmission-station connection capacitybasis operator calculated · network state unknown · comparability class dk_energinet_tso_capacityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Feb 2026
Retrieved / confirmed
2026-09-26 05:56 UTClast confirmed unchanged 2026-09-26 05:56 UTC
Source health
Stale
Provenance
dk_energinet_tso_capacityrecord RIL_132:existing_grid · payload sha256 ab96563d2e47…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: Source: Energinet (www.energidataservice.dk) (last updated 2026-02-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: grid precondition
existing_grid
Operator note: hours with zero consumption capacity
0
Operator note: source field
cap_cons_MW
Operator note: zero with no zero hours
true

Offtake · Load (any) · Available

0 MW

Granted

The operator's latest published dataset reports 0 MW under methodology dk_energinet_tso_capacity_2026.

Firmness
Unknown
Horizon
Now (snapshot) · variant: reinforced_grid
Methodology
dk_energinet_tso_capacity_2026Energinet transmission-station connection capacitybasis operator calculated · network state unknown · comparability class dk_energinet_tso_capacityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Feb 2026
Retrieved / confirmed
2026-09-26 05:56 UTClast confirmed unchanged 2026-09-26 05:56 UTC
Source health
Stale
Provenance
dk_energinet_tso_capacityrecord RIL_132:reinforced_grid · payload sha256 2fe98e85b9ca…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: Source: Energinet (www.energidataservice.dk) (last updated 2026-02-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: grid precondition
reinforced_grid
Operator note: hours with zero consumption capacity
0
Operator note: source field
cap_cons_MW
Operator note: zero with no zero hours
true

Offtake · Load (any) · Available

0%

Published in percent; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0 percent under methodology dk_energinet_tso_capacity_2026.

Firmness
Unknown
Horizon
Now (snapshot) · season: summer · variant: existing_grid:0006_100mw
Methodology
dk_energinet_tso_capacity_2026Energinet transmission-station connection capacitybasis operator calculated · network state unknown · comparability class dk_energinet_tso_capacityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Feb 2026
Retrieved / confirmed
2026-09-26 05:56 UTClast confirmed unchanged 2026-09-26 05:56 UTC
Source health
Stale
Provenance
dk_energinet_tso_capacityrecord RIL_132:existing_grid · payload sha256 ab96563d2e47…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: Source: Energinet (www.energidataservice.dk) (last updated 2026-02-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: grid precondition
existing_grid
Operator note: hours
00-06
Operator note: hours with zero consumption capacity
0
Operator note: plant size mw
100
Operator note: source field
cap_cons_su_0006_100MW_pct
Operator note: zero with no zero hours
true

Offtake · Load (any) · Available

0%

Published in percent; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0 percent under methodology dk_energinet_tso_capacity_2026.

Firmness
Unknown
Horizon
Now (snapshot) · season: summer · variant: existing_grid:0006_300mw
Methodology
dk_energinet_tso_capacity_2026Energinet transmission-station connection capacitybasis operator calculated · network state unknown · comparability class dk_energinet_tso_capacityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Feb 2026
Retrieved / confirmed
2026-09-26 05:56 UTClast confirmed unchanged 2026-09-26 05:56 UTC
Source health
Stale
Provenance
dk_energinet_tso_capacityrecord RIL_132:existing_grid · payload sha256 ab96563d2e47…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: Source: Energinet (www.energidataservice.dk) (last updated 2026-02-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: grid precondition
existing_grid
Operator note: hours
00-06
Operator note: hours with zero consumption capacity
0
Operator note: plant size mw
300
Operator note: source field
cap_cons_su_0006_300MW_pct
Operator note: zero with no zero hours
true

Offtake · Load (any) · Available

0%

Published in percent; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0 percent under methodology dk_energinet_tso_capacity_2026.

Firmness
Unknown
Horizon
Now (snapshot) · season: summer · variant: existing_grid:0617_100mw
Methodology
dk_energinet_tso_capacity_2026Energinet transmission-station connection capacitybasis operator calculated · network state unknown · comparability class dk_energinet_tso_capacityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Feb 2026
Retrieved / confirmed
2026-09-26 05:56 UTClast confirmed unchanged 2026-09-26 05:56 UTC
Source health
Stale
Provenance
dk_energinet_tso_capacityrecord RIL_132:existing_grid · payload sha256 ab96563d2e47…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: Source: Energinet (www.energidataservice.dk) (last updated 2026-02-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: grid precondition
existing_grid
Operator note: hours
06-17
Operator note: hours with zero consumption capacity
0
Operator note: plant size mw
100
Operator note: source field
cap_cons_su_0617_100MW_pct
Operator note: zero with no zero hours
true

Offtake · Load (any) · Available

0%

Published in percent; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0 percent under methodology dk_energinet_tso_capacity_2026.

Firmness
Unknown
Horizon
Now (snapshot) · season: summer · variant: existing_grid:0617_300mw
Methodology
dk_energinet_tso_capacity_2026Energinet transmission-station connection capacitybasis operator calculated · network state unknown · comparability class dk_energinet_tso_capacityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Feb 2026
Retrieved / confirmed
2026-09-26 05:56 UTClast confirmed unchanged 2026-09-26 05:56 UTC
Source health
Stale
Provenance
dk_energinet_tso_capacityrecord RIL_132:existing_grid · payload sha256 ab96563d2e47…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: Source: Energinet (www.energidataservice.dk) (last updated 2026-02-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: grid precondition
existing_grid
Operator note: hours
06-17
Operator note: hours with zero consumption capacity
0
Operator note: plant size mw
300
Operator note: source field
cap_cons_su_0617_300MW_pct
Operator note: zero with no zero hours
true

Offtake · Load (any) · Available

0%

Published in percent; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0 percent under methodology dk_energinet_tso_capacity_2026.

Firmness
Unknown
Horizon
Now (snapshot) · season: summer · variant: existing_grid:1721_100mw
Methodology
dk_energinet_tso_capacity_2026Energinet transmission-station connection capacitybasis operator calculated · network state unknown · comparability class dk_energinet_tso_capacityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Feb 2026
Retrieved / confirmed
2026-09-26 05:56 UTClast confirmed unchanged 2026-09-26 05:56 UTC
Source health
Stale
Provenance
dk_energinet_tso_capacityrecord RIL_132:existing_grid · payload sha256 ab96563d2e47…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: Source: Energinet (www.energidataservice.dk) (last updated 2026-02-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: grid precondition
existing_grid
Operator note: hours
17-21
Operator note: hours with zero consumption capacity
0
Operator note: plant size mw
100
Operator note: source field
cap_cons_su_1721_100MW_pct
Operator note: zero with no zero hours
true

Offtake · Load (any) · Available

0%

Published in percent; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0 percent under methodology dk_energinet_tso_capacity_2026.

Firmness
Unknown
Horizon
Now (snapshot) · season: summer · variant: existing_grid:1721_300mw
Methodology
dk_energinet_tso_capacity_2026Energinet transmission-station connection capacitybasis operator calculated · network state unknown · comparability class dk_energinet_tso_capacityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Feb 2026
Retrieved / confirmed
2026-09-26 05:56 UTClast confirmed unchanged 2026-09-26 05:56 UTC
Source health
Stale
Provenance
dk_energinet_tso_capacityrecord RIL_132:existing_grid · payload sha256 ab96563d2e47…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: Source: Energinet (www.energidataservice.dk) (last updated 2026-02-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: grid precondition
existing_grid
Operator note: hours
17-21
Operator note: hours with zero consumption capacity
0
Operator note: plant size mw
300
Operator note: source field
cap_cons_su_1721_300MW_pct
Operator note: zero with no zero hours
true

Offtake · Load (any) · Available

0%

Published in percent; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0 percent under methodology dk_energinet_tso_capacity_2026.

Firmness
Unknown
Horizon
Now (snapshot) · season: summer · variant: existing_grid:2100_100mw
Methodology
dk_energinet_tso_capacity_2026Energinet transmission-station connection capacitybasis operator calculated · network state unknown · comparability class dk_energinet_tso_capacityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Feb 2026
Retrieved / confirmed
2026-09-26 05:56 UTClast confirmed unchanged 2026-09-26 05:56 UTC
Source health
Stale
Provenance
dk_energinet_tso_capacityrecord RIL_132:existing_grid · payload sha256 ab96563d2e47…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: Source: Energinet (www.energidataservice.dk) (last updated 2026-02-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: grid precondition
existing_grid
Operator note: hours
21-00
Operator note: hours with zero consumption capacity
0
Operator note: plant size mw
100
Operator note: source field
cap_cons_su_2100_100MW_pct
Operator note: zero with no zero hours
true

Offtake · Load (any) · Available

0%

Published in percent; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0 percent under methodology dk_energinet_tso_capacity_2026.

Firmness
Unknown
Horizon
Now (snapshot) · season: summer · variant: existing_grid:2100_300mw
Methodology
dk_energinet_tso_capacity_2026Energinet transmission-station connection capacitybasis operator calculated · network state unknown · comparability class dk_energinet_tso_capacityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Feb 2026
Retrieved / confirmed
2026-09-26 05:56 UTClast confirmed unchanged 2026-09-26 05:56 UTC
Source health
Stale
Provenance
dk_energinet_tso_capacityrecord RIL_132:existing_grid · payload sha256 ab96563d2e47…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: Source: Energinet (www.energidataservice.dk) (last updated 2026-02-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: grid precondition
existing_grid
Operator note: hours
21-00
Operator note: hours with zero consumption capacity
0
Operator note: plant size mw
300
Operator note: source field
cap_cons_su_2100_300MW_pct
Operator note: zero with no zero hours
true

Offtake · Load (any) · Available

0%

Published in percent; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0 percent under methodology dk_energinet_tso_capacity_2026.

Firmness
Unknown
Horizon
Now (snapshot) · season: winter · variant: existing_grid:0006_100mw
Methodology
dk_energinet_tso_capacity_2026Energinet transmission-station connection capacitybasis operator calculated · network state unknown · comparability class dk_energinet_tso_capacityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Feb 2026
Retrieved / confirmed
2026-09-26 05:56 UTClast confirmed unchanged 2026-09-26 05:56 UTC
Source health
Stale
Provenance
dk_energinet_tso_capacityrecord RIL_132:existing_grid · payload sha256 ab96563d2e47…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: Source: Energinet (www.energidataservice.dk) (last updated 2026-02-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: grid precondition
existing_grid
Operator note: hours
00-06
Operator note: hours with zero consumption capacity
0
Operator note: plant size mw
100
Operator note: source field
cap_cons_wi_0006_100MW_pct
Operator note: zero with no zero hours
true

Offtake · Load (any) · Available

0%

Published in percent; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0 percent under methodology dk_energinet_tso_capacity_2026.

Firmness
Unknown
Horizon
Now (snapshot) · season: winter · variant: existing_grid:0006_300mw
Methodology
dk_energinet_tso_capacity_2026Energinet transmission-station connection capacitybasis operator calculated · network state unknown · comparability class dk_energinet_tso_capacityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Feb 2026
Retrieved / confirmed
2026-09-26 05:56 UTClast confirmed unchanged 2026-09-26 05:56 UTC
Source health
Stale
Provenance
dk_energinet_tso_capacityrecord RIL_132:existing_grid · payload sha256 ab96563d2e47…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: Source: Energinet (www.energidataservice.dk) (last updated 2026-02-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: grid precondition
existing_grid
Operator note: hours
00-06
Operator note: hours with zero consumption capacity
0
Operator note: plant size mw
300
Operator note: source field
cap_cons_wi_0006_300MW_pct
Operator note: zero with no zero hours
true

Offtake · Load (any) · Available

0%

Published in percent; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0 percent under methodology dk_energinet_tso_capacity_2026.

Firmness
Unknown
Horizon
Now (snapshot) · season: winter · variant: existing_grid:0617_100mw
Methodology
dk_energinet_tso_capacity_2026Energinet transmission-station connection capacitybasis operator calculated · network state unknown · comparability class dk_energinet_tso_capacityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Feb 2026
Retrieved / confirmed
2026-09-26 05:56 UTClast confirmed unchanged 2026-09-26 05:56 UTC
Source health
Stale
Provenance
dk_energinet_tso_capacityrecord RIL_132:existing_grid · payload sha256 ab96563d2e47…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: Source: Energinet (www.energidataservice.dk) (last updated 2026-02-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: grid precondition
existing_grid
Operator note: hours
06-17
Operator note: hours with zero consumption capacity
0
Operator note: plant size mw
100
Operator note: source field
cap_cons_wi_0617_100MW_pct
Operator note: zero with no zero hours
true

Offtake · Load (any) · Available

0%

Published in percent; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0 percent under methodology dk_energinet_tso_capacity_2026.

Firmness
Unknown
Horizon
Now (snapshot) · season: winter · variant: existing_grid:0617_300mw
Methodology
dk_energinet_tso_capacity_2026Energinet transmission-station connection capacitybasis operator calculated · network state unknown · comparability class dk_energinet_tso_capacityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Feb 2026
Retrieved / confirmed
2026-09-26 05:56 UTClast confirmed unchanged 2026-09-26 05:56 UTC
Source health
Stale
Provenance
dk_energinet_tso_capacityrecord RIL_132:existing_grid · payload sha256 ab96563d2e47…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: Source: Energinet (www.energidataservice.dk) (last updated 2026-02-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: grid precondition
existing_grid
Operator note: hours
06-17
Operator note: hours with zero consumption capacity
0
Operator note: plant size mw
300
Operator note: source field
cap_cons_wi_0617_300MW_pct
Operator note: zero with no zero hours
true

Offtake · Load (any) · Available

0%

Published in percent; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0 percent under methodology dk_energinet_tso_capacity_2026.

Firmness
Unknown
Horizon
Now (snapshot) · season: winter · variant: existing_grid:1721_100mw
Methodology
dk_energinet_tso_capacity_2026Energinet transmission-station connection capacitybasis operator calculated · network state unknown · comparability class dk_energinet_tso_capacityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Feb 2026
Retrieved / confirmed
2026-09-26 05:56 UTClast confirmed unchanged 2026-09-26 05:56 UTC
Source health
Stale
Provenance
dk_energinet_tso_capacityrecord RIL_132:existing_grid · payload sha256 ab96563d2e47…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: Source: Energinet (www.energidataservice.dk) (last updated 2026-02-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: grid precondition
existing_grid
Operator note: hours
17-21
Operator note: hours with zero consumption capacity
0
Operator note: plant size mw
100
Operator note: source field
cap_cons_wi_1721_100MW_pct
Operator note: zero with no zero hours
true

Offtake · Load (any) · Available

0%

Published in percent; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0 percent under methodology dk_energinet_tso_capacity_2026.

Firmness
Unknown
Horizon
Now (snapshot) · season: winter · variant: existing_grid:1721_300mw
Methodology
dk_energinet_tso_capacity_2026Energinet transmission-station connection capacitybasis operator calculated · network state unknown · comparability class dk_energinet_tso_capacityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Feb 2026
Retrieved / confirmed
2026-09-26 05:56 UTClast confirmed unchanged 2026-09-26 05:56 UTC
Source health
Stale
Provenance
dk_energinet_tso_capacityrecord RIL_132:existing_grid · payload sha256 ab96563d2e47…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: Source: Energinet (www.energidataservice.dk) (last updated 2026-02-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: grid precondition
existing_grid
Operator note: hours
17-21
Operator note: hours with zero consumption capacity
0
Operator note: plant size mw
300
Operator note: source field
cap_cons_wi_1721_300MW_pct
Operator note: zero with no zero hours
true

Offtake · Load (any) · Available

0%

Published in percent; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0 percent under methodology dk_energinet_tso_capacity_2026.

Firmness
Unknown
Horizon
Now (snapshot) · season: winter · variant: existing_grid:2100_100mw
Methodology
dk_energinet_tso_capacity_2026Energinet transmission-station connection capacitybasis operator calculated · network state unknown · comparability class dk_energinet_tso_capacityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Feb 2026
Retrieved / confirmed
2026-09-26 05:56 UTClast confirmed unchanged 2026-09-26 05:56 UTC
Source health
Stale
Provenance
dk_energinet_tso_capacityrecord RIL_132:existing_grid · payload sha256 ab96563d2e47…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: Source: Energinet (www.energidataservice.dk) (last updated 2026-02-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: grid precondition
existing_grid
Operator note: hours
21-00
Operator note: hours with zero consumption capacity
0
Operator note: plant size mw
100
Operator note: source field
cap_cons_wi_2100_100MW_pct
Operator note: zero with no zero hours
true

Offtake · Load (any) · Available

0%

Published in percent; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0 percent under methodology dk_energinet_tso_capacity_2026.

Firmness
Unknown
Horizon
Now (snapshot) · season: winter · variant: existing_grid:2100_300mw
Methodology
dk_energinet_tso_capacity_2026Energinet transmission-station connection capacitybasis operator calculated · network state unknown · comparability class dk_energinet_tso_capacityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Feb 2026
Retrieved / confirmed
2026-09-26 05:56 UTClast confirmed unchanged 2026-09-26 05:56 UTC
Source health
Stale
Provenance
dk_energinet_tso_capacityrecord RIL_132:existing_grid · payload sha256 ab96563d2e47…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: Source: Energinet (www.energidataservice.dk) (last updated 2026-02-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: grid precondition
existing_grid
Operator note: hours
21-00
Operator note: hours with zero consumption capacity
0
Operator note: plant size mw
300
Operator note: source field
cap_cons_wi_2100_300MW_pct
Operator note: zero with no zero hours
true

Offtake · Load (any) · Available

0%

Published in percent; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0 percent under methodology dk_energinet_tso_capacity_2026.

Firmness
Unknown
Horizon
Now (snapshot) · season: summer · variant: reinforced_grid:0006_100mw
Methodology
dk_energinet_tso_capacity_2026Energinet transmission-station connection capacitybasis operator calculated · network state unknown · comparability class dk_energinet_tso_capacityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Feb 2026
Retrieved / confirmed
2026-09-26 05:56 UTClast confirmed unchanged 2026-09-26 05:56 UTC
Source health
Stale
Provenance
dk_energinet_tso_capacityrecord RIL_132:reinforced_grid · payload sha256 2fe98e85b9ca…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: Source: Energinet (www.energidataservice.dk) (last updated 2026-02-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: grid precondition
reinforced_grid
Operator note: hours
00-06
Operator note: hours with zero consumption capacity
0
Operator note: plant size mw
100
Operator note: source field
cap_cons_su_0006_100MW_pct
Operator note: zero with no zero hours
true

Offtake · Load (any) · Available

0%

Published in percent; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0 percent under methodology dk_energinet_tso_capacity_2026.

Firmness
Unknown
Horizon
Now (snapshot) · season: summer · variant: reinforced_grid:0006_300mw
Methodology
dk_energinet_tso_capacity_2026Energinet transmission-station connection capacitybasis operator calculated · network state unknown · comparability class dk_energinet_tso_capacityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Feb 2026
Retrieved / confirmed
2026-09-26 05:56 UTClast confirmed unchanged 2026-09-26 05:56 UTC
Source health
Stale
Provenance
dk_energinet_tso_capacityrecord RIL_132:reinforced_grid · payload sha256 2fe98e85b9ca…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: Source: Energinet (www.energidataservice.dk) (last updated 2026-02-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: grid precondition
reinforced_grid
Operator note: hours
00-06
Operator note: hours with zero consumption capacity
0
Operator note: plant size mw
300
Operator note: source field
cap_cons_su_0006_300MW_pct
Operator note: zero with no zero hours
true

Offtake · Load (any) · Available

0%

Published in percent; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0 percent under methodology dk_energinet_tso_capacity_2026.

Firmness
Unknown
Horizon
Now (snapshot) · season: summer · variant: reinforced_grid:0617_100mw
Methodology
dk_energinet_tso_capacity_2026Energinet transmission-station connection capacitybasis operator calculated · network state unknown · comparability class dk_energinet_tso_capacityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Feb 2026
Retrieved / confirmed
2026-09-26 05:56 UTClast confirmed unchanged 2026-09-26 05:56 UTC
Source health
Stale
Provenance
dk_energinet_tso_capacityrecord RIL_132:reinforced_grid · payload sha256 2fe98e85b9ca…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: Source: Energinet (www.energidataservice.dk) (last updated 2026-02-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: grid precondition
reinforced_grid
Operator note: hours
06-17
Operator note: hours with zero consumption capacity
0
Operator note: plant size mw
100
Operator note: source field
cap_cons_su_0617_100MW_pct
Operator note: zero with no zero hours
true

Offtake · Load (any) · Available

0%

Published in percent; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0 percent under methodology dk_energinet_tso_capacity_2026.

Firmness
Unknown
Horizon
Now (snapshot) · season: summer · variant: reinforced_grid:0617_300mw
Methodology
dk_energinet_tso_capacity_2026Energinet transmission-station connection capacitybasis operator calculated · network state unknown · comparability class dk_energinet_tso_capacityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Feb 2026
Retrieved / confirmed
2026-09-26 05:56 UTClast confirmed unchanged 2026-09-26 05:56 UTC
Source health
Stale
Provenance
dk_energinet_tso_capacityrecord RIL_132:reinforced_grid · payload sha256 2fe98e85b9ca…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: Source: Energinet (www.energidataservice.dk) (last updated 2026-02-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: grid precondition
reinforced_grid
Operator note: hours
06-17
Operator note: hours with zero consumption capacity
0
Operator note: plant size mw
300
Operator note: source field
cap_cons_su_0617_300MW_pct
Operator note: zero with no zero hours
true

Offtake · Load (any) · Available

0%

Published in percent; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0 percent under methodology dk_energinet_tso_capacity_2026.

Firmness
Unknown
Horizon
Now (snapshot) · season: summer · variant: reinforced_grid:1721_100mw
Methodology
dk_energinet_tso_capacity_2026Energinet transmission-station connection capacitybasis operator calculated · network state unknown · comparability class dk_energinet_tso_capacityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Feb 2026
Retrieved / confirmed
2026-09-26 05:56 UTClast confirmed unchanged 2026-09-26 05:56 UTC
Source health
Stale
Provenance
dk_energinet_tso_capacityrecord RIL_132:reinforced_grid · payload sha256 2fe98e85b9ca…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: Source: Energinet (www.energidataservice.dk) (last updated 2026-02-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: grid precondition
reinforced_grid
Operator note: hours
17-21
Operator note: hours with zero consumption capacity
0
Operator note: plant size mw
100
Operator note: source field
cap_cons_su_1721_100MW_pct
Operator note: zero with no zero hours
true

Offtake · Load (any) · Available

0%

Published in percent; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0 percent under methodology dk_energinet_tso_capacity_2026.

Firmness
Unknown
Horizon
Now (snapshot) · season: summer · variant: reinforced_grid:1721_300mw
Methodology
dk_energinet_tso_capacity_2026Energinet transmission-station connection capacitybasis operator calculated · network state unknown · comparability class dk_energinet_tso_capacityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Feb 2026
Retrieved / confirmed
2026-09-26 05:56 UTClast confirmed unchanged 2026-09-26 05:56 UTC
Source health
Stale
Provenance
dk_energinet_tso_capacityrecord RIL_132:reinforced_grid · payload sha256 2fe98e85b9ca…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: Source: Energinet (www.energidataservice.dk) (last updated 2026-02-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: grid precondition
reinforced_grid
Operator note: hours
17-21
Operator note: hours with zero consumption capacity
0
Operator note: plant size mw
300
Operator note: source field
cap_cons_su_1721_300MW_pct
Operator note: zero with no zero hours
true

Offtake · Load (any) · Available

0%

Published in percent; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0 percent under methodology dk_energinet_tso_capacity_2026.

Firmness
Unknown
Horizon
Now (snapshot) · season: summer · variant: reinforced_grid:2100_100mw
Methodology
dk_energinet_tso_capacity_2026Energinet transmission-station connection capacitybasis operator calculated · network state unknown · comparability class dk_energinet_tso_capacityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Feb 2026
Retrieved / confirmed
2026-09-26 05:56 UTClast confirmed unchanged 2026-09-26 05:56 UTC
Source health
Stale
Provenance
dk_energinet_tso_capacityrecord RIL_132:reinforced_grid · payload sha256 2fe98e85b9ca…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: Source: Energinet (www.energidataservice.dk) (last updated 2026-02-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: grid precondition
reinforced_grid
Operator note: hours
21-00
Operator note: hours with zero consumption capacity
0
Operator note: plant size mw
100
Operator note: source field
cap_cons_su_2100_100MW_pct
Operator note: zero with no zero hours
true

Offtake · Load (any) · Available

0%

Published in percent; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0 percent under methodology dk_energinet_tso_capacity_2026.

Firmness
Unknown
Horizon
Now (snapshot) · season: summer · variant: reinforced_grid:2100_300mw
Methodology
dk_energinet_tso_capacity_2026Energinet transmission-station connection capacitybasis operator calculated · network state unknown · comparability class dk_energinet_tso_capacityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Feb 2026
Retrieved / confirmed
2026-09-26 05:56 UTClast confirmed unchanged 2026-09-26 05:56 UTC
Source health
Stale
Provenance
dk_energinet_tso_capacityrecord RIL_132:reinforced_grid · payload sha256 2fe98e85b9ca…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: Source: Energinet (www.energidataservice.dk) (last updated 2026-02-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: grid precondition
reinforced_grid
Operator note: hours
21-00
Operator note: hours with zero consumption capacity
0
Operator note: plant size mw
300
Operator note: source field
cap_cons_su_2100_300MW_pct
Operator note: zero with no zero hours
true

Offtake · Load (any) · Available

0%

Published in percent; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0 percent under methodology dk_energinet_tso_capacity_2026.

Firmness
Unknown
Horizon
Now (snapshot) · season: winter · variant: reinforced_grid:0006_100mw
Methodology
dk_energinet_tso_capacity_2026Energinet transmission-station connection capacitybasis operator calculated · network state unknown · comparability class dk_energinet_tso_capacityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Feb 2026
Retrieved / confirmed
2026-09-26 05:56 UTClast confirmed unchanged 2026-09-26 05:56 UTC
Source health
Stale
Provenance
dk_energinet_tso_capacityrecord RIL_132:reinforced_grid · payload sha256 2fe98e85b9ca…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: Source: Energinet (www.energidataservice.dk) (last updated 2026-02-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: grid precondition
reinforced_grid
Operator note: hours
00-06
Operator note: hours with zero consumption capacity
0
Operator note: plant size mw
100
Operator note: source field
cap_cons_wi_0006_100MW_pct
Operator note: zero with no zero hours
true

Offtake · Load (any) · Available

0%

Published in percent; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0 percent under methodology dk_energinet_tso_capacity_2026.

Firmness
Unknown
Horizon
Now (snapshot) · season: winter · variant: reinforced_grid:0006_300mw
Methodology
dk_energinet_tso_capacity_2026Energinet transmission-station connection capacitybasis operator calculated · network state unknown · comparability class dk_energinet_tso_capacityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Feb 2026
Retrieved / confirmed
2026-09-26 05:56 UTClast confirmed unchanged 2026-09-26 05:56 UTC
Source health
Stale
Provenance
dk_energinet_tso_capacityrecord RIL_132:reinforced_grid · payload sha256 2fe98e85b9ca…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: Source: Energinet (www.energidataservice.dk) (last updated 2026-02-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: grid precondition
reinforced_grid
Operator note: hours
00-06
Operator note: hours with zero consumption capacity
0
Operator note: plant size mw
300
Operator note: source field
cap_cons_wi_0006_300MW_pct
Operator note: zero with no zero hours
true

Offtake · Load (any) · Available

0%

Published in percent; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0 percent under methodology dk_energinet_tso_capacity_2026.

Firmness
Unknown
Horizon
Now (snapshot) · season: winter · variant: reinforced_grid:0617_100mw
Methodology
dk_energinet_tso_capacity_2026Energinet transmission-station connection capacitybasis operator calculated · network state unknown · comparability class dk_energinet_tso_capacityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Feb 2026
Retrieved / confirmed
2026-09-26 05:56 UTClast confirmed unchanged 2026-09-26 05:56 UTC
Source health
Stale
Provenance
dk_energinet_tso_capacityrecord RIL_132:reinforced_grid · payload sha256 2fe98e85b9ca…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: Source: Energinet (www.energidataservice.dk) (last updated 2026-02-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: grid precondition
reinforced_grid
Operator note: hours
06-17
Operator note: hours with zero consumption capacity
0
Operator note: plant size mw
100
Operator note: source field
cap_cons_wi_0617_100MW_pct
Operator note: zero with no zero hours
true

Offtake · Load (any) · Available

0%

Published in percent; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0 percent under methodology dk_energinet_tso_capacity_2026.

Firmness
Unknown
Horizon
Now (snapshot) · season: winter · variant: reinforced_grid:0617_300mw
Methodology
dk_energinet_tso_capacity_2026Energinet transmission-station connection capacitybasis operator calculated · network state unknown · comparability class dk_energinet_tso_capacityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Feb 2026
Retrieved / confirmed
2026-09-26 05:56 UTClast confirmed unchanged 2026-09-26 05:56 UTC
Source health
Stale
Provenance
dk_energinet_tso_capacityrecord RIL_132:reinforced_grid · payload sha256 2fe98e85b9ca…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: Source: Energinet (www.energidataservice.dk) (last updated 2026-02-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: grid precondition
reinforced_grid
Operator note: hours
06-17
Operator note: hours with zero consumption capacity
0
Operator note: plant size mw
300
Operator note: source field
cap_cons_wi_0617_300MW_pct
Operator note: zero with no zero hours
true

Offtake · Load (any) · Available

0%

Published in percent; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0 percent under methodology dk_energinet_tso_capacity_2026.

Firmness
Unknown
Horizon
Now (snapshot) · season: winter · variant: reinforced_grid:1721_100mw
Methodology
dk_energinet_tso_capacity_2026Energinet transmission-station connection capacitybasis operator calculated · network state unknown · comparability class dk_energinet_tso_capacityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Feb 2026
Retrieved / confirmed
2026-09-26 05:56 UTClast confirmed unchanged 2026-09-26 05:56 UTC
Source health
Stale
Provenance
dk_energinet_tso_capacityrecord RIL_132:reinforced_grid · payload sha256 2fe98e85b9ca…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: Source: Energinet (www.energidataservice.dk) (last updated 2026-02-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: grid precondition
reinforced_grid
Operator note: hours
17-21
Operator note: hours with zero consumption capacity
0
Operator note: plant size mw
100
Operator note: source field
cap_cons_wi_1721_100MW_pct
Operator note: zero with no zero hours
true

Offtake · Load (any) · Available

0%

Published in percent; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0 percent under methodology dk_energinet_tso_capacity_2026.

Firmness
Unknown
Horizon
Now (snapshot) · season: winter · variant: reinforced_grid:1721_300mw
Methodology
dk_energinet_tso_capacity_2026Energinet transmission-station connection capacitybasis operator calculated · network state unknown · comparability class dk_energinet_tso_capacityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Feb 2026
Retrieved / confirmed
2026-09-26 05:56 UTClast confirmed unchanged 2026-09-26 05:56 UTC
Source health
Stale
Provenance
dk_energinet_tso_capacityrecord RIL_132:reinforced_grid · payload sha256 2fe98e85b9ca…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: Source: Energinet (www.energidataservice.dk) (last updated 2026-02-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: grid precondition
reinforced_grid
Operator note: hours
17-21
Operator note: hours with zero consumption capacity
0
Operator note: plant size mw
300
Operator note: source field
cap_cons_wi_1721_300MW_pct
Operator note: zero with no zero hours
true

Offtake · Load (any) · Available

0%

Published in percent; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0 percent under methodology dk_energinet_tso_capacity_2026.

Firmness
Unknown
Horizon
Now (snapshot) · season: winter · variant: reinforced_grid:2100_100mw
Methodology
dk_energinet_tso_capacity_2026Energinet transmission-station connection capacitybasis operator calculated · network state unknown · comparability class dk_energinet_tso_capacityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Feb 2026
Retrieved / confirmed
2026-09-26 05:56 UTClast confirmed unchanged 2026-09-26 05:56 UTC
Source health
Stale
Provenance
dk_energinet_tso_capacityrecord RIL_132:reinforced_grid · payload sha256 2fe98e85b9ca…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: Source: Energinet (www.energidataservice.dk) (last updated 2026-02-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: grid precondition
reinforced_grid
Operator note: hours
21-00
Operator note: hours with zero consumption capacity
0
Operator note: plant size mw
100
Operator note: source field
cap_cons_wi_2100_100MW_pct
Operator note: zero with no zero hours
true

Offtake · Load (any) · Available

0%

Published in percent; no MW figure is derived from it.

Granted

The operator's latest published dataset reports 0 percent under methodology dk_energinet_tso_capacity_2026.

Firmness
Unknown
Horizon
Now (snapshot) · season: winter · variant: reinforced_grid:2100_300mw
Methodology
dk_energinet_tso_capacity_2026Energinet transmission-station connection capacitybasis operator calculated · network state unknown · comparability class dk_energinet_tso_capacityNot additive across assets. The method accounts for reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Operator’s date
1 Feb 2026
Retrieved / confirmed
2026-09-26 05:56 UTClast confirmed unchanged 2026-09-26 05:56 UTC
Source health
Stale
Provenance
dk_energinet_tso_capacityrecord RIL_132:reinforced_grid · payload sha256 2fe98e85b9ca…Operator’s publication (opens the operator’s site)
Licence
CC BY 4.0Attribution: Source: Energinet (www.energidataservice.dk) (last updated 2026-02-01)
Decision context
Not binding · indicative · a formal connection study is required
Operator note: grid precondition
reinforced_grid
Operator note: hours
21-00
Operator note: hours with zero consumption capacity
0
Operator note: plant size mw
300
Operator note: source field
cap_cons_wi_2100_300MW_pct
Operator note: zero with no zero hours
true

History

Served series only

Injection · Generation (any) · Available

current 696 MW

26 Sep 2026: 696 MW
26 Sep 2026range 696–696 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current696 MW

Time axis: when we observed each value, not the operator’s effective date.

Injection · Unknown · Available

current 47%

26 Sep 2026: 47%
26 Sep 2026range 47–47%26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current47%

Time axis: when we observed each value, not the operator’s effective date.

Injection · Unknown · Available

current 45%

26 Sep 2026: 45%
26 Sep 2026range 45–45%26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current45%

Time axis: when we observed each value, not the operator’s effective date.

Injection · Unknown · Available

current 90%

26 Sep 2026: 90%
26 Sep 2026range 90–90%26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current90%

Time axis: when we observed each value, not the operator’s effective date.

Injection · Unknown · Available

current 89%

26 Sep 2026: 89%
26 Sep 2026range 89–89%26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current89%

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available

current 0 MW

26 Sep 2026: 0 MW
26 Sep 2026range 0–0 MW26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0 MW

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available

current 0%

26 Sep 2026: 0%
26 Sep 2026range 0–0%26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0%

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available

current 0%

26 Sep 2026: 0%
26 Sep 2026range 0–0%26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0%

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available

current 0%

26 Sep 2026: 0%
26 Sep 2026range 0–0%26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0%

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available

current 0%

26 Sep 2026: 0%
26 Sep 2026range 0–0%26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0%

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available

current 0%

26 Sep 2026: 0%
26 Sep 2026range 0–0%26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0%

Time axis: when we observed each value, not the operator’s effective date.

Offtake · Load (any) · Available

current 0%

26 Sep 2026: 0%
26 Sep 2026range 0–0%26 Sep 2026
1 published value, as a table
Observed fromUntilValue
26 Sep 2026current0%

Time axis: when we observed each value, not the operator’s effective date.

The first 12 of 44 served series with a history. The history route returns every one of them.

Through the API

curl "https://api.gridcapacityapi.com/v1/substations/sub_06gdrjaybsvyq32pe9bdrwrw1m/capacity" \  -H "Authorization: Bearer gc_live_..."
Rislev 132 kV substation: grid capacity (Energinet) · GridCapacity API