SSEN Generation Availability and Network Capacity — Methodology Statement
gb_ssen_headroom_dashboard_2025 · v2025-09SSEN pulls together its asset management database, network mapping, ongoing projects, customer application/quotation database and EHV network modelling into an estimate of demand and generation headroom per substation, with the contracted and connected positions beside it.
- Capacity basis
- operator calculated
- Network state
- unknown
- Binding
- No
- Additive across assets
- No — do not sum these figures
- The method accounts for
- reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
- Comparability class
- gb_ssen_headroom_dashboard
- Documentation
- Operator’s method (opens the operator’s site)
The operator’s own caveats
- Our map provides an indication of the networks capability to connect large-scale developments to major substations.
- All information and data on the data portal is provided “as is”.
- We do not accept responsibility for any errors or omissions in the information and data or for any results obtained, decisions made or actions taken following review and use of this information and data.