Northern Powergrid LTDS Capacity Heatmap
gb_npg_ltds_heatmap_2026 · v2026-05 (LTDS May 2026, data_processed 2026-07-06)NPg's implementation of the Ofgem LTDS Capacity Heatmap (Capacity Heatmaps Appendix 1 – Information Model): firm, available and reverse-power-flow capacity per substation in MVA, with contracted demand and generation. NPg publishes no method statement for it beyond the standard's definition; how it relates to NPg's own heat-map headroom (in MW for generation) is not stated, so the two are not comparable.
- Capacity basis
- operator calculated
- Network state
- unknown
- Binding
- No
- Additive across assets
- No — do not sum these figures
- The method accounts for
- reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
- Comparability class
- gb_npg_ltds_heatmap
- Documentation
- Operator’s method (opens the operator’s site)