EDF SEI HTB injection status per poste
fr_edf_sei_htb_injection · vCRE délibération n° 2019-275 (dataset updated 2026-08-25)Whether injection capacity remains on the transmission (HTB) network at the poste, taking into account projects with a connection request not yet commissioned and the capacity reserved under the S2REnR/S3REnR. Published as a word, not a number.
- Capacity basis
- operator published
- Network state
- unknown
- Binding
- No
- Additive across assets
- No — do not sum these figures
- The method accounts for
- reserved: yes · allocated: yes · pre-reserved: not stated · pending requests: yes
- Comparability class
- fr_edf_sei_htb_status
- Documentation
- Operator’s method (opens the operator’s site)
The operator’s own caveats
- Des offres de raccordement sont suspendues sur certaines zones, en raison de la saturation des capacités techniques du réseau.