es_eredes_access_capacity

E-Redes: Capacidad de acceso de generación y de demanda por nudo

Published by Hidrocantábrico Distribución Eléctrica, S.A.U. / ES / Monthly

Grantedcommercial_use_with_attributionHealthy

Generation and firm demand access capacity in MW at every busbar (substation x voltage level) of Hidrocantábrico Distribución Eléctrica, S.A.U.'s network, in the format CNMC made mandatory (BOE-A-2025-9913): available, occupied and admitted-not-resolved (generation also split by technology), with regulated substation codes and UTM coordinates.

E-Redes: Capacidad de acceso de generación y de demanda por nudo on a map

The 198 located assets in this publication, coloured by the spare capacity Hidrocantábrico Distribución Eléctrica, S.A.U. publishes for each today. Click a point for its figure.

The map of Europe →

Loading the map…

What is withheld, and why

Nothing is withheld. Values are served with the attribution the licence asks for: Fuente: Hidrocantábrico Distribución Eléctrica, S.A.U. (R1-008), publicación conforme a la Resolución CNMC de 30-04-2025. Keep it with any figure you show.

Switched to commercial_use_with_attribution on 2026-10-02 on the owner's report that the operator gave permission by telephone. No written confirmation is on file: ask for one, and an objection from the operator means rights_override = blocked the same day. The evidence below is the operator's published terms as read before the call. Before: The legal notice allows downloading and copying for personal and private use only; reproduction, distribution, transmission or modification for public or commercial purposes is excluded even with attribution, and no licence of any kind is granted. The bucket carries no terms of its own. Archived, never served, until the operator authorises reuse in writing.

Licence and rights evidence

Attribution
Fuente: Hidrocantábrico Distribución Eléctrica, S.A.U. (R1-008), publicación conforme a la Resolución CNMC de 30-04-2025required
Technical access
Yes
Commercial use
Yes
May be cached
Yes
May be redistributed
Yes
Derived data allowed
Yes

Evidence

Methodology

2 version(s)

E-Redes firm demand access capacity per busbar

es_eredes_dem_2026 · vCircular 1/2024, Especificaciones de Detalle (Resolution 8-06-2025); BOE-A-2025-9913 format

The distributor's monthly firm demand access capacity per busbar under CNMC's common methodology, in the regulated file format: firm available, occupied and admitted but not yet evaluated, in MW.

Capacity basis
operator calculated
Network state
unknown
Binding
No
Additive across assets
No. Do not sum these figures.
The method accounts for
reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Comparability class
es_rdd_demand_firm_access_cir1_2024

The operator’s own caveats

  • The operator's website disclaimer gives no warranty of accuracy or currency.

E-Redes generation access capacity per busbar

es_eredes_gen_2026 · vCircular 1/2021, Especificaciones de Detalle; BOE-A-2025-9913 format

The distributor's monthly generation access capacity per busbar under CNMC's common methodology, in the regulated file format: available, occupied and admitted but not yet resolved (also by technology), in MW.

Capacity basis
operator calculated
Network state
unknown
Binding
No
Additive across assets
No. Do not sum these figures.
The method accounts for
reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Comparability class
es_rdd_generation_access_cir1_2021

The operator’s own caveats

  • The operator's website disclaimer gives no warranty of accuracy or currency; no capacity-specific caveat is published beside the files.

How the publication maps to the model

availability types
["available","allocated","requested"]
binding
false
directions
["injection","offtake"]
firmness
["firm","unknown"]
geometry precision
exact
includes reserved projects
null
non additive
true
notes
["The 17 regulated generation columns and 15 demand columns of BOE-A-2025-9913, checked by header and read by position: capacidad (firme) disponible (available), ocupada (allocated), admitida y no resuelta / no evaluada (requested). Demand is firm by rule; generation firmness is not stated.","The generation file splits 'admitida y no resuelta' by technology in four extra columns (Eólica, Solar, Almacenamiento, Otras): four more requested series. 'Eólica' and 'Solar' do not say onshore/offshore or PV/thermal and the vocabulary has no plain wind or solar, so their technology is unknown, with the operator's label in the variant and in details; Almacenamiento is storage_other, Otras other. The total stays authoritative, and when the splits do not add up to it the total and the splits are flagged split_inconsistent.","A busbar is (Subestación, Nivel de Tensión); Subestación is the regulated substation code (Circular 8/2021 form B3). A busbar in both files is one asset with two records.","'Capacidad comprometida' (tender or Just-Transition reservation), 'Nudo limitado por Scc' and 'Nudo 0*' are flags on the available value; Comentarios travels in details.","The CSVs are Windows-1252; coordinates are ETRS89 UTM zone 30 (EPSG:25830), chosen from the province. E-Redes' demand file has no name column and puts the substation name in COMENTARIOS (every row of the 2026-09 file), so there it is the name; its generation splits disagree with the total in 35 of 191 rows (flagged). E-Redes published around the 19th-22nd of each month in 2026-01..08, later than the rule's five days. The 2026-09 files also carry one substation (SE PLANS DE LA SALA, Sallent) under registry code R1-363, which no CNMC layer lists: its four rows are rejected with that reason until the operator behind the code is established."]
spatial scope
busbar
technologies
["generic_generation","unknown","storage_other","other","generic_load"]
units
["MW"]

Query this source

curl "https://api.gridcapacityapi.com/v1/capacity/search?source=es_eredes_access_capacity&limit=20" \  -H "Authorization: Bearer gc_live_..."