e-distribución — Capacidad de acceso de generación y de demanda por nudo

Published by Edistribución Redes Digitales, S.L.U. · ES · Monthly

Archived, pending reviewpending_reviewHealthy

Generation and firm demand access capacity in MW at every busbar (substation x voltage level) of the Endesa group's distribution networks, in the format CNMC made mandatory (BOE-A-2025-9913): available, occupied and admitted-not-resolved, with regulated substation codes, UTM coordinates and the operator's comments.

What is withheld, and why

Every value from this source is withheld. The operator’s terms do not clearly allow us to redistribute its figures, and when signals conflict the more restrictive reading wins until the operator confirms otherwise in writing. Records are still listed — with capacity.value null, access.status "withheld" and a link to the publication — so you know the operator publishes something there.

The publication is still read and kept, because operators overwrite their files and a history not recorded when it happened can never be recovered. If reuse is cleared, customers get the history as well as the present.

The legal notice allows private reproduction for one's own use only: nothing may be passed on to third parties, no reproduction, distribution or public communication without authorisation, no commercial use, no decompiling of the databases. Archived, never served, until e-distribución authorises reuse in writing.

Licence and rights evidence

Attribution
Fuente: Edistribución Redes Digitales, S.L.U. (R1-299), publicación conforme a la Resolución CNMC de 30-04-2025required
Technical access
Yes
Commercial use
No
May be cached
Not established
May be redistributed
No
Derived data allowed
Not established

Evidence

Methodology

2 version(s)

e-distribución firm demand access capacity per busbar

es_edistribucion_dem_2026 · vCircular 1/2024, Especificaciones de Detalle (Resolution 8-06-2025); BOE-A-2025-9913 format

The distributor's monthly firm demand access capacity per busbar under CNMC's common methodology, in the regulated file format: firm available, occupied and admitted but not yet evaluated, in MW.

Capacity basis
operator calculated
Network state
unknown
Binding
No
Additive across assets
No — do not sum these figures
The method accounts for
reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Comparability class
es_rdd_demand_firm_access_cir1_2024

The operator’s own caveats

  • e-distribución: the information is indicative and the capacities are neither cumulative nor simultaneous.

e-distribución generation access capacity per busbar

es_edistribucion_gen_2026 · vCircular 1/2021, Especificaciones de Detalle; BOE-A-2025-9913 format

The distributor's monthly generation access capacity per busbar under CNMC's common methodology, in the regulated file format: available, occupied and admitted but not yet resolved, in MW.

Capacity basis
operator calculated
Network state
unknown
Binding
No
Additive across assets
No — do not sum these figures
The method accounts for
reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Comparability class
es_rdd_generation_access_cir1_2021

The operator’s own caveats

  • e-distribución: the information is indicative; capacities are neither cumulative nor simultaneous and do not consider limits in other distributors' networks or the transmission network; a node may already be committed by requests admitted before publication; requests on 0 MW nodes are rejected.

How the publication maps to the model

availability types
["available","allocated","requested"]
binding
false
directions
["injection","offtake"]
firmness
["firm","unknown"]
geometry precision
exact
includes reserved projects
null
non additive
true
notes
["The 17 regulated generation columns and 15 demand columns of BOE-A-2025-9913, checked by header and read by position: capacidad (firme) disponible (available), ocupada (allocated: connected plus permits in force), admitida y no resuelta / no evaluada (requested). Demand is firm by rule ('capacidad firme'); generation firmness is not stated.","A busbar is (Subestación, Nivel de Tensión): Subestación is the regulated substation code (Circular 8/2021 form B3), unique per substation; a busbar in both files is one asset with two records. The name comes from the extra column 'Nombre Subestación'.","'Capacidad comprometida por cuestiones regulatorias' (tender or Just-Transition reservation), 'Nudo limitado por Scc' and 'Nudo 0*' are flags on the available value; Comentarios travels in details.","Coordinates are ETRS89 UTM in the zone the rule assigns by province — 30 (EPSG:25830) for the peninsula, Ceuta and Melilla, 28 (EPSG:25828) for Canarias, 31 (EPSG:25831) for Baleares — chosen from the province, never from the numbers. e-distribución's regulated Provincia / Municipio columns hold INE codes, against the rule; the names are in its extra columns.","A decimal comma; XLSX cells (one month had only an XLSX link) are rounded off float noise to nine places."]
spatial scope
busbar
technologies
["generic_generation","generic_load"]
units
["MW"]

Query this source

curl "https://api.gridcapacityapi.com/v1/capacity/search?source=es_edistribucion_access_capacity&limit=20" \  -H "Authorization: Bearer gc_live_..."