de_transnetbw_netzanschlusskarte

TransnetBW: Netzanschlusskarte

Published by TransnetBW GmbH / DE / When the operator updates it

Grantedcommercial_use_with_attributionHealthy

TransnetBW's map of 52 substations in Baden-Württemberg: whether a new transmission connection is possible, and, where it is, the earliest year (2032 or 2035) and the available injection and load capacity bands (MW) at 380 kV.

TransnetBW: Netzanschlusskarte on a map

The 48 located assets in this publication, coloured by the spare capacity TransnetBW GmbH publishes for each today. Click a point for its figure.

The map of Europe →

Loading the map…

What is withheld, and why

Nothing is withheld. Values are served with the attribution the licence asks for: Quelle: TransnetBW GmbH, Netzanschlusskarte (transnetbw.de), Stand laut Karte; unverbindlich. Lage: GeoNames (CC BY 4.0). Keep it with any figure you show.

Switched to commercial_use_with_attribution on 2026-10-02 on the owner's report that the operator gave permission by telephone. No written confirmation is on file: ask for one, and an objection from the operator means rights_override = blocked the same day. The evidence below is the operator's published terms as read before the call. Before: Linking allowed; reproduction needs TransnetBW's prior consent. Locations are GeoNames localities (CC BY 4.0, credited above).

Licence and rights evidence

Attribution
Quelle: TransnetBW GmbH, Netzanschlusskarte (transnetbw.de), Stand laut Karte; unverbindlich. Lage: GeoNames (CC BY 4.0)required
Technical access
Yes
Commercial use
Yes
May be cached
Yes
May be redistributed
Yes
Derived data allowed
Yes

Evidence

Methodology

1 version(s)

TransnetBW Netzanschlusskarte: connection possibilities at 380 kV substations

de_transnetbw_netzanschlusskarte_2026 · vStand 05/2026

TransnetBW's best assessment, as of 1 April 2026, of where a new connection to its transmission grid is possible, the earliest commissioning year, and the available injection and load capacity in bands, per substation.

Capacity basis
operator published
Network state
unknown
Binding
No
Additive across assets
No. Do not sum these figures.
The method accounts for
reserved: not stated · allocated: not stated · pre-reserved: not stated · pending requests: not stated
Comparability class
de_tso_connection_bands

The operator’s own caveats

  • Non-binding; there is no claim to a connection, and every request needs a connection study.

How the publication maps to the model

availability types
["available"]
binding
false
directions
["injection","offtake"]
firmness
["unknown"]
geometry precision
municipality
includes reserved projects
null
non additive
true
notes
["One asset per substation tooltip, keyed by TransnetBW's slug (tooltip-uw-daxlanden).","Capacity is published in bands, kept as a status per direction with TransnetBW's band as the label and its bounds in details.band_min_mw / band_max_mw: \"0 MW\" unavailable, \"< 500 MW\" limited, 500 MW and up available.","Green (mittelfristig) and yellow (langfristig) substations state an earliest commissioning year; their bands are target-year values for that year. Red substations (nicht verfügbar) carry no figures and are unavailable now in both directions.","The connection type (n-0, n-1, 'keine BESS!') and notes such as 'temporärer Anschluss bis 2045' travel as attributes and details.","The map is schematic. Each substation is placed at the GeoNames locality it is named after (municipality precision); Oberwald, Rheinau, Weier and Mühlhausen match several places and are not placed."]
spatial scope
substation
technologies
["generic_generation","generic_load"]
units
["status"]

Query this source

curl "https://api.gridcapacityapi.com/v1/capacity/search?source=de_transnetbw_netzanschlusskarte&limit=20" \  -H "Authorization: Bearer gc_live_..."